New construction (drilling) of artesian well No. 2 for water supply of the Chornomorsk urban territorial community at the address: Odesa region, Odessa district, Molodizhne village, Sanzhiyska doroha st., 3-B.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the new construction (drilling) of artesian well No. 1 in the village of Molodizhne to ensure water supply to the Chornomorsk urban territorial community. The implementation of the project will allow creating an autonomous source of drinking water, independent of centralized systems and the stability of electricity supply. The project is aimed at solving the problem of the vulnerability of the existing water supply system in conditions of martial law, emergency power outages and possible damage to critical infrastructure. The lack of sufficient backup creates risks of interruptions in the provision of water to the population. As a result of the project, a stable and uninterrupted water supply will be ensured, a reserve source of water for the population will be created, and the sustainability of the community's life support system will be increased. The expected productivity of the well is up to 110 m³/day, which will allow covering the needs of a significant part of the population.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Improving the equality of wealth distribution, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Population in the geographical area of influence of the project
70 thous. people
Number of IDPs in the geographical area of impact of the project
8 thous. people
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.1 Reconstruct, modernize and constantly restore the infrastructure of housing and communal services, housing stock and improvements, update the material and technical base of enterprises in this area to ensure stable and high-quality housing and communal services and comfort for community residents.
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New construction (drilling) of an artesian well
Technical Solution 2
Construction of a local seawater desalination plant
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]