Purchase of a school bus for the Lisovodsky Lyceum, a Support Institution


Sector
Education and science
Stream
Unhindered access to quality education - school buses
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

Due to the optimization of the network of secondary education institutions of the Horodok territorial community, planned for 2026, in particular, the closure of the Kreminyansk branch of the Lisovodsky Lyceum of the Horodok City Council, there is a need to ensure access to quality education and transport 49 students of the Kreminyansk branch to the closest secondary education institution to their place of residence - the Lisovodsky Lyceum. The project contributes to the optimization of the educational network.

The purpose of the project

Main Goal:

Improving the equality of wealth distribution

Secondary Goal:

Ensuring inclusiveness and equal opportunities, Improving the quality of services, Reducing territorial or social gaps

Description of the purpose of the project and ways to achieve it

In connection with the optimization of the educational institution, in order to ensure the ability to safely and timely get to the supporting institution, the Lisovodsky Lyceum, by taking a school bus to the educational institution and back.

Problems and solutions resulting from project implementation

Ensuring equal access to quality education for children in rural areas of the community, the opportunity to study in a better-equipped support school contributes to increasing students' academic achievement, minimizing the risks associated with children getting to school on their own, and ensuring safe transportation in accordance with all state standards.

Socio-economic context

Indicator

Value

Number of people who will use the service

49 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Unhindered access to quality education - school buses

Strategic document

Стратегія розвитку територіальної громади

Task

3.4.1. To create a modern educational space common to the entire community, where the existing infrastructure and teaching skills can be best used

Project objectives

Indicator
Base value
Target value
Number of students being picked up
19 human
49 human

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Метод прямого підрахунку
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
19 human
Annual demand for services/infrastructure
2
49 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
economic analysis.docx
30.03.2026
13:15:55 UTC

Alternative technical solutions

Technical Solution 1

Purchase of a school bus for the Lisovodsky Lyceum, a Support Institution

Technical Solution 2

Ordering transportation services from a private carrier

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)4'000'000 UAH1'500'000 UAH
For preparation0 UAH10'000 UAH
For implementation4'000'000 UAH1'490'000 UAH
Project operation and closure cost350'000 UAH1'500'000 UAH
For operation350'000 UAH1'500'000 UAH
Average annual costs350'000 UAH0 UAH
Project duration, incl.7 months7 months
Deadline for developing a FFS1 month1 month
Implementation period6 months6 months
Service life120 months9 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget4'350'000 UAH3'000'000 UAH
Project cost (preparation and implementation)4'000'000 UAH1'500'000 UAH
For preparation0 UAH10'000 UAH
For implementation4'000'000 UAH1'490'000 UAH
Project operation and closure cost350'000 UAH1'500'000 UAH
For operation350'000 UAH1'500'000 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitСередня вартість проєкту на одного отримувача послуги
Service Unit Cost81'632 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Yes, negotiations are already underway.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Economic riskDefinedUndefined
Operational riskDefinedUndefined

Team involvement

How exactly are/will stakeholders be involved?
Meetings with local authorities

[Response was provided in the Investment Feasibility Study]

Public consultations

[Response was provided in the Investment Feasibility Study]

Public hearings

[Response was provided in the Investment Feasibility Study]

When are/will engagement activities be taking place?
At the project preparation stage

[Response was provided in the Investment Feasibility Study]

How is/will the public be informed about the importance of participation and available channels for feedback?
Official websites

[Response was provided in the Investment Feasibility Study]

Social networks

[Response was provided in the Investment Feasibility Study]

Local media

[Response was provided in the Investment Feasibility Study]

Are public hearings being held/will they be held (offline, online)?
Yes, offline.

[Response was provided in the Investment Feasibility Study]

громадські слухання проведено офлайн
Who will attend the public hearings?
Representatives of public organizations

[Response was provided in the Investment Feasibility Study]

Community representatives

[Response was provided in the Investment Feasibility Study]

Government officials

[Response was provided in the Investment Feasibility Study]

Public hearings have already been held
Yes

[Response was provided in the Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
31/03/2026SP-L-310326-5B79E24FCommunity SPInvestment Feasibility StudyIncludeInclude in sector portfolio-
03/04/2026SP-N-030426-BF63F0D2State SPInvestment Feasibility StudyInclude--
03/04/2026SPP-L-030426-663AFDFBCommunity SPPInvestment Feasibility StudyIncludeIncluded in the EPP by the decision of the Investment Council-