General information
Description of the project
The project is aimed at creating a modern and safe infrastructure for the elderly and people with disabilities who need external care and support.
The following activities are planned to be implemented within the project:
- reconstruction and major repairs of buildings to accommodate an inpatient unit to improve living conditions and provide social services;
- improvement of adjacent areas taking into account the principles of inclusion and leisure;
- major repairs of the dining room and catering unit;
- creation and equipping of sports grounds and workshops.
As a result of the evacuation of the population of the Selydivskaya MTG to safer regions, a significant number of single elderly citizens and people with disabilities found themselves without proper living conditions. They need not only safe housing and care, but also opportunities for active leisure, socialization and health maintenance.
Expected results:
- creation of modern infrastructure for permanent or temporary residence of the elderly and people with disabilities;
- improvement of living conditions through major repairs and reconstruction;
- formation of an inclusive and accessible environment in the departments;
- providing opportunities for physical activity, creative development and social integration of wards;
- improvement of the quality of life and level of social protection of the most vulnerable categories of the population.
The purpose of the project
Main Goal:
Improving the equality of wealth distribution
Secondary Goal:
Ensuring inclusiveness and equal opportunities, Creation of new jobs through project implementation, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of users from low-mobility population groups
50 human
Number of jobs, including for IDPs
42 human
Number of people who will use the service
100 human
Number of IDP users
100 human
Strategic Case
Strategic feasibility of the project
Sector
Social sector
Subsector
Social services
Stream
Development of residential care facilities for the elderly and people with disabilities
Strategic document
Регіональна стратегія розвитку
Task
2.3.1 Improving the quality of life of people in need of special social, medical, psychological and rehabilitation assistance, especially those who suffered as a result of hostilities in the region
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Reconstruction and major repairs with landscaping and infrastructure creation
Technical Solution 2
Construction of new facilities
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]