General information
Description of the project
The public investment project involves the restoration of an apartment building damaged by hostilities. According to the adjusted design and estimate documentation, the total cost is 32,055.460 thousand UAH, of which emergency works worth 15,992.246 thousand UAH have already been completed. The project covers the remaining construction works: comprehensive thermal modernization, reinforcement of load-bearing structures, renewal of engineering networks, as well as ensuring physical accessibility and landscaping of the adjacent territory for the safe living of residents.
The purpose of the project
Main Goal:
Rebuilding the damaged/destroyed
Secondary Goal:
Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
150 human
Number of IDP users
31 human
Strategic Case
Strategic feasibility of the project
Sector
Housing
Subsector
Housing Reconstruction
Stream
Restoration of apartment buildings damaged as a result of the armed aggression of the Russian Federation
Strategic document
Стратегія розвитку територіальної громади
Task
A.3.1.2. Implementation of updated standards for the accessibility of residential buildings with safe, comfortable living conditions, taking into account the needs of different groups of citizens.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of an apartment building at 203-D Yablunska Street, Bucha, Bucha district, Kyiv region - measures to eliminate accidents in the apartment building
Technical Solution 2
Reconstruction of an apartment building at 203d Yablunska Street in Bucha with partial change of geometric parameters and redevelopment.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]