Major repairs of damaged sections of household gravity sewer collectors passing through the territory of the main sewage pumping station at the address: Odesa region, Odessa district, Chornomorsk city, 23 Parkova st.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The detailed design envisages the relocation of the existing emergency domestic collector DN 800 mm with a total length of 126.2 meters using the “rehabilitation” method, pulling a Spirokor DN 600 mm polyethylene pipe into the body of the existing reinforced concrete pipe. The pipes are pulled through technological pits located near the existing inspection wells.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
8000 thous. people
Number of people who will use the service
70000 thous. people
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.1 Reconstruct, modernize and constantly restore the infrastructure of housing and communal services, housing stock and improvements, update the material and technical base of enterprises in this area to ensure stable and high-quality housing and communal services and comfort for community residents.
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of damaged sections of household gravity sewer collectors passing through the territory of the main sewage pumping station at the address: Odesa region, Odessa district, Chornomorsk city, 23 Parkova st.
Technical Solution 2
Construction of new sections of household gravity sewer collectors passing through the territory of the main sewage pumping station at the address: Odesa region, Odessa district, Chornomorsk city, 23 Parkova st.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]