Technical re-equipment of primary electrical connections of substation No. 71, Bucha, Yablunska 15-V


Sector
Energy Sector
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The existing transformer substation is located separately and consists of separate premises: RU-10 kV, RU-0.4 kV, transformer premises T1 and T2. Ventilation of the transformer premises with natural air movement through louvered grilles. Address of the facility: Bucha, Yablunska 15-V. The facility is in the communal property of the Bucha City Council. The transformer substation was damaged as a result of the armed aggression of Russia approximately on 01.03.2022 and was destroyed and requires reconstruction measures. 

The purpose of the project

Main goal:

Rebuilding the damaged/destroyed

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

Improving the technical level and reliability of the community's electrical network by updating primary electrical connections and implementing modern technical solutions that will ensure stable and uninterrupted power supply. Currently, the primary electrical connections of the transformer substation have a high degree of wear, which leads to frequent failures, power losses and reduced reliability of power supply. Outdated equipment does not meet modern requirements for energy efficiency, safety and automation. The implementation of the project will eliminate these shortcomings, bringing the technical condition of the substation to a modern level, which will ensure the continuity of electricity supply, reduce losses and improve the quality of power supply for the population and enterprises of the community.

Problems and solutions resulting from project implementation

High degree of wear and tear of transformer substation equipment. Low reliability and stability of power supply. Lack of modern automation and monitoring systems. Insufficient network capacity when the load increases. Increased electricity losses and frequent emergency shutdowns.

Socio-economic context

Indicator

Value

Capacity

400 kW

Strategic Case

Strategic feasibility of the project

Sector

Energy Sector

Subsector

Electric power industry

Stream

Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)

Strategic document

Task

A.2.5.3. Implementation of Municipal Energy Plan measures

Project objectives

Indicator
Base value
Target value
Economic justification

Alternative technical solutions

Technical Solution 1

Technical re-equipment of primary electrical connections of substation No. 71, Bucha, Yablunska 15-V

Technical Solution 2

Construction of a new transformer substation

Total costs10'132'007 UAH27'500'000 UAH
  • For preparation
  • 350'000 UAH2'000'000 UAH
  • For implementation
  • 8'101'007 UAH20'000'000 UAH
  • For operation
  • 1'680'000 UAH500'000 UAH
  • For closing
  • 1'000 UAH5'000'000 UAH
    Average annual costs840'000 UAH1'000'000 UAH
    Project duration, incl.9 months48 months
  • Deadline for developing a FFS
  • 3 months24 months
  • Implementation period
  • 6 months24 months
    Service life120 months240 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Financial justification

    Total project budget

    Total preliminary budget10'132'007 UAH27'500'000 UAH
    Capital costs10'132'007 UAH27'500'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation350'000 UAH2'000'000 UAH
    For implementation8'101'007 UAH20'000'000 UAH
    For operation1'680'000 UAH500'000 UAH
    For closing1'000 UAH5'000'000 UAH

    Average project cost per service recipient

    Service UnitРемонт трансформаторної підстанції
    Service Unit Cost7'400'000 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH