"New construction of parking lots and installation of landscaping elements at the address: Odesa region, Odessa district, Nadlymanske village, B. Khmelnytskyi street"


Sector
Transport Sector
Stream
Construction of transport infrastructure to create safe conditions for the population
Maturity level
92
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project "New construction of parking lots and arrangement of landscaping elements at the address: Odesa region, Odessa district, Nadlymanske village, B. Khmelnytskyi st." provides for the arrangement of a parking area near the Nadlymanske Lyceum in order to ensure safe and comfortable conditions for the placement of vehicles of students, employees and visitors to the educational institution. The project includes the arrangement of parking spaces, access roads, sidewalks, landscaping and other landscaping elements in accordance with modern requirements and standards.

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Improving the equality of wealth distribution, Ensuring inclusiveness and equal opportunities

Description of the purpose of the project and ways to achieve it

The purpose of the project “New construction of parking lots and arrangement of landscaping elements at the address: Odesa region, Odessa district, Nadlymanske village, B. Khmelnytskyi street” is to create safe, orderly and convenient conditions for parking vehicles near the Nadlymanske Lyceum, as well as to improve the landscaping of the surrounding area, taking into account the requirements of barrier-free, sanitary, environmental and operational standards. The implementation of the project is aimed at increasing the level of comfort, safety and accessibility of the educational institution for students, teaching staff and visitors, as well as reducing the traffic load on the street and road network of the settlement. The method of achieving the goal involves a set of measures for the construction of new parking lots with modern hard surfaces, the arrangement of access roads, pedestrian zones and landscaping elements, such as landscaping, the installation of small architectural forms, urns, benches, drainage trays and outdoor lighting. The project also provides for the arrangement of places for people with reduced mobility in accordance with the requirements of state building codes, which will ensure inclusiveness and convenience of using the territory. The implementation of the project will allow to regulate traffic flows near the educational institution, reduce the level of spontaneous parking, improve the aesthetic appearance of the territory and create a safe environment for pedestrians and vehicles. In addition, the arrangement of the territory will positively affect the general improvement of the central part of the village of Nadlymanske, will contribute to increasing the level of comfort for community residents and the development of social infrastructure.

Problems and solutions resulting from project implementation

The main problems in this area are the lack of equipped parking spaces for vehicles, which leads to chaotic placement of vehicles, complicates the approach to the lyceum building, creates a danger for pedestrians, in particular students, and worsens the landscaping of the territory. There is also destruction of the coating of the adjacent area due to unregulated movement of cars. As a result of the project, an organized parking area for vehicles will be created, equipped with appropriate landscaping elements, which will ensure convenience and safety of movement, improve the organization of traffic flow, and also increase the level of landscaping and aesthetic appearance of the educational institution's territory.

Socio-economic context

Indicator

Value

Other functional

13 units

Number of people who will use the service

1500 human

Strategic Case

Strategic feasibility of the project

Sector

Transport Sector

Subsector

Road transport and road infrastructure

Stream

Construction of transport infrastructure to create safe conditions for the population

Strategic document

Стратегія розвитку територіальної громади

Task

2.1.4 Ensuring the development of road infrastructure and the establishment of the "Mayaki-Udobne-Nadlymanske" routes

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Expert opinion.pdf
19.12.2025
16:25:45 UTC
General explanatory note.pdf
19.12.2025
16:26:07 UTC

Alternative technical solutions

Technical Solution 1

Construction of 13 parking spaces

Technical Solution 2

Construction of 23 parking spaces

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)3'231'598 UAH5'060'000 UAH
For preparation58'080 UAH60'000 UAH
For implementation3'173'518 UAH5'000'000 UAH
Project operation and closure cost100'000 UAH100'000 UAH
For operation100'000 UAH100'000 UAH
Average annual costs100'000 UAH0 UAH
Project duration, incl.12 months12 months
Deadline for developing a FFS6 months6 months
Implementation period6 months6 months
Service life144 months144 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget3'331'598 UAH5'160'000 UAH
Project cost (preparation and implementation)3'231'598 UAH5'060'000 UAH
For preparation58'080 UAH60'000 UAH
For implementation3'173'518 UAH5'000'000 UAH
Project operation and closure cost100'000 UAH100'000 UAH
For operation100'000 UAH100'000 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitСередня вартість проєкту на одиницю продукції
Service Unit Cost248'584 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
None of the options are applicable
Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
No, I need help.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
19/12/2025SP-L-191225-74BF5057Community SPInvestment Feasibility StudyInclude--
26/12/2025SPP-L-261225-704B663BCommunity SPPInvestment Feasibility StudyInclude-92