Creation of an educational space within the framework of the "New Ukrainian School" reform - Kulykivska territorial community


Sector
Education and science
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

Within the framework of the implementation of the project "New Ukrainian School", funds are allocated for the Horbiv Gymnasium to update the material and technical base of educational institutions. The implementation of the project is aimed at creating a modern, safe and comfortable educational environment, improving the quality of education and ensuring appropriate conditions for the formation of key competencies of education seekers in accordance with the concept of the New Ukrainian School.

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Increasing compliance with modern standards, Improving the quality of services

Description of the purpose of the project and ways to achieve it

The goal is achieved through repairs and the purchase of equipment aimed at updating the modern space.

Problems and solutions resulting from project implementation

Key problems are the outdated educational space, the insufficient level of its technical and digital equipment, as well as the inconsistency of learning conditions with modern requirements and standards. The existing environment does not fully provide opportunities for the implementation of innovative methods and the development of students' digital competencies. The urgency of solving these problems is due to the growing requirements for the quality of education and the need to form skills in students that meet the challenges of today.

Socio-economic context

Indicator

Value

Other social

82 human

Other social

19 human

Other social

1 units

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform

Strategic document

Стратегія розвитку територіальної громади

Task

3.2.1. 3.2.1. Introduction of innovative forms and methods of learning.

Project objectives

Indicator
Base value
Target value
Number of classrooms to be equipped
1 units
1 units
Number of participants in the educational process who will have access to the main educational space
101 units
101 units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Для оцінки попиту на послуги застосовано комплексний підхід, що включав аналіз демографічних даних громади, статистики звернень до закладу, а також прогноз потреб з урахуванням збільшення кількості ВПО.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
101 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Guarantee_letter_for_co-financing_NUSH.pdf
26.02.2026
10:50:03 UTC

Alternative technical solutions

Technical Solution 1

Creation of an educational space within the framework of the "New Ukrainian School" reform - Kulykivska territorial community

Technical Solution 2

Rental of teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform

Total costs345'953 UAH600'003 UAH
  • For preparation
  • 1 UAH1 UAH
  • For implementation
  • 345'950 UAH600'000 UAH
  • For operation
  • 1 UAH1 UAH
  • For closing
  • 1 UAH1 UAH
    Average annual costs10'000 UAH1'000 UAH
    Project duration, incl.4 months3 months
  • Deadline for developing a FFS
  • 1 month1 month
  • Implementation period
  • 3 months2 months
    Service life60 months24 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget345'953 UAH600'003 UAH
    Capital costs345'953 UAH600'003 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation1 UAH1 UAH
    For implementation345'950 UAH600'000 UAH
    For operation1 UAH1 UAH
    For closing1 UAH1 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitВартість одиниці послуги
    Service Unit Cost1'001 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds345'950 UAH0 UAH
    Expected Funds345'950 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Project management - communication with stakeholders

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Yes, successfully implemented 1 or more similar projects

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    None of the options are applicable
    Is there an understanding of where to find relevant experts and consultants?
    Partially, we are considering options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Financial riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    26/02/2026SP-L-260226-8B65D2F1Community SPInvestment Feasibility StudyIncludeThe project meets the requirements
    27/02/2026SPP-L-270226-1BFB4E12Community SPPInvestment Feasibility StudyInclude-