General information
Description of the project
The project provides for the repair of the digester-clarifier No. 9 of the treatment facilities. For settling wastewater, fermentation and compaction of the precipitated sediment, the treatment facilities use clarifiers-digesters, in which wastewater after the grates and sand traps is fed through distribution chambers through trays into the central pipe of the clarifier-digester. The water pressure (0.4-0.6 m) created by the difference in liquid levels above the pipe entrance and in the clarifier, provides a wastewater velocity in the central pipe of 0.5-0.7 m/sec, necessary for the suction of air from the atmosphere into the liquid. The wastewater saturated with air is directed from the central pipe by a reflecting shield into the flocculation chamber, where mixing and enlargement of suspension particles in the wastewater occurs for 20 minutes. After that, the wastewater enters the settling chamber, where a layer of sediment is formed. The duration of the liquid in the settling chamber is at least 40 minutes. The clarified liquid is collected by a peripheral tray and discharged through a pipe to the next stage of purification. The sediment that has fallen to the bottom of the clarifier is sent through a pipe under hydrostatic pressure to the receiving tank of the sludge pumping station, from where it is fed by a pump through a pressure pipe to the upper zone of the digester (evenly around the circumference), where it undergoes fermentation. The fermented sediment is discharged through a sludge pipe after 7-10 days. The relative location of the clarifier and digester (the clarifier tank is located in the center of the digester tank) allows the sediment to be isolated from direct contact with the clarified liquid and to use the heat of wastewater during sludge fermentation, which is carried out without artificial heating. At the moment: metal trays that feed wastewater from the distribution chamber to the central clarifier pipe, the central clarifier pipe, the reflecting shield, the flocculation chamber, the clarified wastewater outlet pipe have become completely unusable. The listed equipment needs to be replaced. The sludge supply pipeline to the digester from the sludge pumping station is in a condition suitable for further operation after being fixed to the newly installed clarifier-digester fence. The equipment must be installed in accordance with DSTU-N B V.2.5-68:2012 "Guidelines for the construction, installation and quality control of pipelines of external water supply and sewage networks". The operating mode of the treatment plants is 24 hours a day, all year round.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
15700 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.1.; 2.1.2. ; 2.2.2.; 2.2.3. Development and implementation of renewable energy sources; Implementation of energy saving measures; Conservation of water resources; 2.2.3. Environmental protection
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Overhaul of the clarifier-decomposer No. 9 of the complex of treatment facilities of the city of Voznesensk, Mykolaiv region at the address: village of Rakove, Zavodska st., 19-21
Technical Solution 2
Complete replacement of clarifier-digestor No. 9 with a modern modular installation for biological wastewater treatment from polymer tanks
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]