New construction of the civil defense building of the Novoselivka preschool educational institution (nursery-kindergarten) of the Raukhiv village council of the Bereziv district of the Odessa region at the address: Odesa region, Bereziv district, Novoselivka village, Nova-77a street.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Working The project "New construction of a civil defense building of the Novoselivka preschool educational institution (nursery) of the Raukhiv settlement council of the Berezivsky district of the Odessa region at the address: Odesa region, Berezivsky district, Novoselivka village, Nova street, 77-a! was developed on the basis of the following data: urban planning conditions and restrictions, design tasks, based on legal documents, topographic and geodetic surveys of the site, the total area of the site within the designed boundaries is 0.7081 hectares. Architectural and construction solutions for the working project for the construction of the shelter were developed on the basis of the design tasks, construction, sanitary, fire protection requirements of current norms and rules, as well as tasks of specialized groups.
A building with underground premises with overall dimensions of 30.05*16.1m of the II degree of fire resistance. The following premises are provided as shelters: main premises for shelters, bathrooms for boys and girls, a universal bathroom, a ventilation room, an electrical panel room, a first aid station, as well as rooms for storing food and water, rooms for storing dirty and and clean clothes. underground premises are provided with two dispersed exits. To enable unhindered access to the MGN, a disabled lift for descent to underground premises is provided. equipment is provided for at seats-100% of educators and staff; on bunk beds-transformers and on chairs at tables - 100% of pupils. Additionally, a play area (3*4m) a toy cupboard and shoe shelf are provided. Placement of technological equipment, calculation of the area of the main room and sanitary facilities, was carried out in accordance with DBN V.2.2-5:2023. The implementation of the project is aimed at ensuring simultaneous shelter in a protective building of civil defense in the event of an emergency
The purpose of the project
Main Goal:
Improving the equality of wealth distribution
Secondary Goal:
Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capital expenditure per year
35579302 thous. UAH value of services per year
Number of people who will use the service
120 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
Preschool education
Stream
New construction of the civil defense building of the Novoselivskyi preschool educational institution (nursery-kindergarten) of the Raukhiv village council, Berezivskyi district, Odessa region
Strategic document
National Strategy for Building a Safe and Healthy Educational Environment in the New Ukrainian School
Task
1 Creating a safe, healthy educational environment
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New construction of the civil defense building of the Novoselivka preschool educational institution (nursery-kindergarten) of the Raukhiv village council of the Bereziv district of the Odessa region at the address: Odesa region, Bereziv district, Novoselivka village, Nova-77a street.
Technical Solution 2
Warehouses in peacetime
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Risk assessment
Team involvement
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]