Construction of a water supply network along Romodanivska, Arkhangelska, Gayova, Genicheska, Debaltsevska streets in the city of Chernivtsi (adjustment for I, II and III launch complexes)
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The project envisages the creation of a centralized system of domestic, drinking and fire-fighting water supply. The source of water supply is the existing water supply network, to which the new infrastructure is connected. The investment project envisages the construction and phased commissioning of an external water supply network in the residential area of the city of Chernivtsi in order to provide the population with high-quality drinking water, increase the reliability of engineering infrastructure and create conditions for sustainable development of the territory. The water supply network is laid underground along streets and driveways. The total length of the water supply network is over 2.2 km, which ensures the connection of existing and prospective consumers. The connection of individual residential buildings will be carried out in stages according to separate projects.
The purpose of the project
Main goal:
Meeting demand
Secondary goal:
Capacity building, Contribution to climate or environmental goals, Creation of new facilities and services, Improving the equality of wealth distribution, Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capacity
19.3 m3
Other functional
7044 m3
Other functional
9 units
Other functional
2259 m
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Development and modernization of the engineering infrastructure of the urban community
Strategic document
Стратегія розвитку територіальної громади
Task
Update existing networks
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Construction of a water supply network along Romodanivska, Arkhangelska, Gayova, Genicheska, Debaltsevska streets in the city of Chernivtsi (adjustment for I, II and III launch complexes)
Technical Solution 2
Preservation of decentralized water supply with local modernization of existing sources
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]