New construction of the water supply network Havrylivka-Lubyanka-Blystavytsia-Bucha-Vorzel in the territory of the Bucha territorial community of Kyiv region
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
By shelling the city of Bucha and the village of Vorzel, the troops of the Russian Federation destroyed the balanced water supply system of the city of Bucha and the village of Vorzel. Water towers, wells, main and distribution water pipes were destroyed. The main part of the existing wells in the territory of the city of Bucha has exhausted its resource (the debit fell to 5-6 m3/h). For reliable water supply of the city of Bucha, a set of works is being carried out that will ensure reliable water supply of the city of Bucha and the village of Vorzel, taking into account the prospective needs of these settlements in drinking water, namely: new construction of a groundwater intake from 6 artesian wells to the Cenomanian aquifer on the territory of the existing sanitary protection zones of the wells of the Gavrylivka hydroelectric complex. (the debit of each well is 40 m3/h) is being carried out by LLC "Ukrbudvodproekt"; pumping station 240 m 3 / h, with the installation of two working pumps of 120 m 3 / h each with cascade inclusion. Also one emergency and one reserve, with automatic inclusion of the reserve on the territory of the hydroelectric power plant in the village of Havrylivka; water supply (two threads) from the village of Havrylivka to the village of Vorzel with an internal diameter of 200 mm, to meet the needs of residents of the Buchansk urban territorial community 240 m 3 / h; a pumping station should be provided at the hydroelectric power plant in the village of Blystavytsia; pumping station of the 2nd lift with clean water tanks with a volume of 3000 m 3 and an organic water purification station with a capacity of 6000 m 3 / day on Lesi Ukrainky Street 28/1 in the village of Vorzel; a water supply that will connect the clean water tanks of the existing pumping station of the 2nd lift on the street. Volodymyr Kovalskyi in the city of Bucha with a designed pumping station of the 2nd lift on Lesi Ukrainky St., 28/1 in the village of Vorzel. Within the framework of this project "New construction of the water supply network Havrylivka-Lubyanka-Blystavytsia-Bucha-Vorzel on the territory of the Bucha territorial community of the Kyiv region", adjustments were made to the project "New construction of the urban water supply system (ringing of clean water tanks on Volodymyr Kovalskyi St. in the city of Bucha and on Lesi Ukrainky St. in the village of Vorzel) on the territory of the Bucha territorial community of the Kyiv region. Adjustments" and included in the project Volume 4. Ringing of clean water tanks on Volodymyr Kovalskyi St. in the city of Bucha and hydroelectric power station on Lesi Ukrainky St., building 28/1a in the village of Vorzel". Also, within the framework of this project, adjustments were made to the project "New construction of a 2nd lift pumping station with clean water tanks and a deironing station with a capacity of 6000 m3/day on Lesi Ukrainky Street, building 28/1a, in the village of Vorzel, Buchanskyi territorial community, Buchanskyi district, Kyiv region" and included in the project in four volumes, namely: as Volume 5 Hydroblock on Lesi Ukrainky Street, building 28/1a in the village of Vorzel. Deironing station with a capacity of 6000 m3/day. These projects are interconnected.
The purpose of the project
Main goal:
Improving the equality of wealth distribution
Secondary goal:
Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
73000 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Task
A.2.3.3. Improving the accessibility of centralized wastewater for the community population
Project objectives
Demand for the service and its dynamics
Alternative technical solutions
Technical Solution 1
A comprehensive infrastructure project to develop and modernize the community's water supply system
Technical Solution 2
Reconstruction and modernization of existing local water supply systems in each settlement
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]