General information
Description of the project
The project is aimed at increasing the reliability and safety of Ukraine's high-voltage energy infrastructure by implementing modern relay protection and control devices (IED) at the facilities of NPP "Ukrenergo" in the most affected regions (Kharkiv, Zaporizhia, Kherson, Mykolaiv regions, etc.). It is also planned to provide remote technical support from Hitachi Energy (Switzerland and Ukraine), which will ensure the effective use of equipment, the development of personnel competencies and the formation of sustainable engineering expertise within Ukrenergo.
The project meets the priorities of the Government of Ukraine regarding the restoration of energy infrastructure and is critically important, since without reliable power supply, the development of any sector of the economy is impossible - from industry to the humanitarian sphere. IED protection allows you to localize accidents and prevent cascading shutdowns of networks, fires or destruction of transformers, reactors and other high-value equipment.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other economic
231448 thous. UAH
Strategic Case
Strategic feasibility of the project
Sector
Energy Sector
Subsector
Electric power industry
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Strategic document
Energy Strategy of Ukraine until 2050
Task
Ensuring a stable, balanced model of operation of the Unified Power System of Ukraine; restoration, development and transformation of the power system, its sustainable operation;; increasing the efficiency of substations
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Interruptible Power Devices (IED) and training for the reconstruction and development of Ukraine's high-voltage electricity transmission network for Ukrenergo NPP
Technical Solution 2
not provided
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]