Energy Sector

The development of the energy sector has a decisive impact on the state of the national economy and the quality of life of the population.
This pipeline will present public investment projects and programs in the energy sector that align with the following areas: fossil fuels, renewable energy sources and alternative fuels, nuclear energy, electricity generation, and the oil and gas industry. These initiatives are aimed at supporting the implementation of the Energy Strategy of Ukraine. The Ministry of Energy of Ukraine is engaged in the preparation and development of projects and programs in these areas, forming a sectoral project pipeline at the national level and subsequently enriching it with public investment projects at the regional and local levels.
Indicative total public investment ceiling is 120'834'620'600 UAH, including funds from the State Fund for Decarbonization and Energy Efficiency Transformation in the amount of 6'930'983'900 UAH, and State Guarantees in the amount of 105'100'000'000 UAH
Responsible Ministry
MINISTRY OF ENERGY OF UKRAINE
Indicative total public investment ceiling
120.8 bln
Project code
Keyword
Initiator
Project coverage area
Number of alternative technical approaches
Initiation date
Budget
Status
State level of SPP
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusInvestment Feasibility Study

Purchase of KRS machines and improvement of energy efficiency of JSC "Ukrgazvydobuvannya"

Project goal
Capacity building.
Geography
Bazylivshchyna village
Initiator
JOINT STOCK COMPANY "UKRGAZVYDOBUVANNYA"
Purchase of cattle breeding machines
Continued use of the existing fleet of cattle breeding machines without upgrading
The Company is purchasing 5 new well workover rigs (WWR) with a lifting capacity of 125 tons and 5 new WWR rigs with a lifting capacity of 180 tons. Due to this, the Company is partially updating its own fleet and receiving 180-ton WWR rigs, which will allow it to carry out well repairs by its own forces at depths > 6000 m. This will also reduce the involvement of external contractors, which, in turn, will lead to cost savings on well workovers and other operations to intensify production. This, in turn, will contribute to increasing (excluding natural decline) natural gas production from existing fields in the most economical way.
Budget15'072'317'240,02 UAH
Implementation period16 months
State level of SPP
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Purchase of gas pumping units for JSC "Ukrtransgaz" (7 GPU)

Project goal
Improving the condition of infrastructure. Increasing compliance with modern standards
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRTRANSGAZ"
purchase of 7 GPA
further use of existing equipment
The purchase of new gas storage units will ensure uninterrupted operation of the compressor shops of underground gas storage facilities and guaranteed gas withdrawal from the underground gas storage facilities at maximum productive levels, especially during critical periods.
Budget8'000'000'000,03 UAH
Implementation period51 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Purchase of gas pumping units for JSC "Ukrtransgaz" (3 gas pumping units with a capacity of 13 MW)

Project goal
Improving the condition of infrastructure. Increasing compliance with modern standards
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRTRANSGAZ"
purchase of 3 HPA with a capacity of 13 MW
further use of existing equipment
The purchase of new gas storage units will ensure uninterrupted operation of the compressor shops of underground gas storage facilities and guaranteed gas withdrawal from the underground gas storage facilities at maximum productive levels, especially during critical periods.
Budget2'131'200'001,02 UAH
Implementation period27 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Purchase of KRS machines to increase the efficiency of capital repairs by our own forces and expand the operational well fund

Project goal
Capacity building. Increasing compliance with modern standards, Increasing compliance with modern standards, Creation of new facilities and services, Improving the quality of services
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Purchase of 30 new KRS machines (65 tons - 26 units, 125 tons - 4 units)
Procurement of services of an external contractor for conducting RRC
Increasing the efficiency and complexity of performing routine and capital repairs of wells, which is a necessary condition for implementing the Company's strategic goals of increasing oil and gas production.
Budget1'407'000'003 UAH
Implementation period24 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Strengthening its own oil service function by updating the fleet of specialized equipment of JSC "Ukrnafta"

Project goal
Increasing compliance with modern standards. Increasing compliance with modern standards, Improving the quality of services
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Renewal of the specialized equipment fleet of JSC "Ukrnafta" through procurement
Procurement of services from external contractors for relevant work
Budget6'530'000'003 UAH
Implementation period30 months
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusInvestment Feasibility Study

Central European Hydrogen Corridor (CEHC)

Project goal
Creation of new facilities and services. Contribution to climate or environmental goals, Introducing innovations and energy-efficient solutions
Geography
Zakarpatska region, Ivano-Frankivska region, Lvivska region
Initiator
LIMITED LIABILITY COMPANY "OPERATOR OF THE GAS TRANSPORT SYSTEM OF UKRAINE"
Repurposing the existing GTS infrastructure for hydrogen transportation
Construction of a new hydrogen pipeline and compressor stations with associated infrastructure
The project includes two main groups of activities: 1. Study of the properties and technical condition of existing GTS facilities (220 km main gas pipeline and compressor station) for the possibility of their use and necessary adaptation measures for hydrogen transportation 2. Implementation of measures to adapt existing GTS facilities for hydrogen transportation: such as replacing crane units on the existing gas pipeline, construction of 37.5 MW of hydrogen compressor capacity at the compressor station.
Budget18'094'146'001 UAH
Implementation period60 months
State level of SPP
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Northern Region Expansion Project

Project goal
Increasing compliance with modern standards.
Geography
Zhytomyrska region, Kyivska region, Cherkaska region
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
Reconstruction and automation of the 330 kV substation "Brovarska", 330 kV substation "Cherkaska" and 330 kV substation "Zhytomyrska", as well as the new construction of the 330 kV substation "Zakhidna"
Not provided
Replacement of outdated primary equipment at substations of NPC «Ukrenergo» with the transition to modern switchgear schemes, installation of an automated process control system, creation of new transit connections, as well as the introduction of physical protection of critical elements of substations from air attacks in order to reduce the risks of emergency situations in the Unified Power System of Ukraine
Budget4'398'300'002 UAH
Implementation period54 months
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

New construction of the 330 kV Kvartsit - Pershotravneva transmission line with the reconstruction of the 330 kV Kvartsit substation and the 330 kV Pershotravneva substation, Kirovohrad and Dnipropetrovsk regions

Project goal
Improving the condition of infrastructure.
Geography
Dnipropetrovska region, Kirovohradska region
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
Construction of the 330 kV Kvartsyt – Pershotravneva overhead line. Reconstruction of the 330 kV substations of the Kvartsyt and Pershotravneva substations with the equipment of the corresponding connections for the possibility of connecting the 330 kV overhead line. Construction of a linear connection on the 330 kV substation of the Kvartsyt substation for connecting the 330 kV overhead line of the South Ukrainian NPP – Kvartsyt No. 1.
Not provided
And the turn. - Construction of the 330 kV Quartzite substation – May Day The estimated length of the 330 kV power line is 108 km. Phase II. – Reconstruction of RU 330 kV Substation "Quartsit" and "May Day" with the equipment of appropriate connections for the possibility of connecting the 330 kV PL. Construction at the 330 kV substation "Quartzite" linear connection for connecting the 330 kV substation of the South Ukrainian NPP – Quartzite No. 1.
Budget1'919'700'002 UAH
Implementation period42 months
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Increasing the stability and reliability of electricity transmission in Ukraine

Project goal
Improving the condition of infrastructure.
Geography
All Ukraine
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
Construction of protected substations and substation control systems, supply and installation of relay protection and automation devices at 16 selected substations, construction of a new backup dispatch center
not provided
development of design documentation in accordance with current Ukrainian norms and standards; construction of underground RPA devices at 16 substations, including those necessary for the substation's own needs; supply of new RPA devices; construction of underground cable ducts; installation and commissioning of the specified devices in new protected underground structures; construction of a backup dispatch center.
Budget13'375'055'802 UAH
Implementation period34 months
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Reconstruction of the 400 kV Mukacheve substation with the introduction of an automated process control system (APCS)

Project goal
Improving the condition of infrastructure.
Geography
Zakarpatska region
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
Reconstruction of the Mukacheve 400 kV substation with the introduction of an automated process management system (ASKTP)
Not provided
Existing equipment of VRU 400 kV, VRU 220 kV, VRU 110 kV, VRU 35 kV and KTP-10 kV PS 400/220/110/35 kV "Mukacheve" morally obsolete and technically obsolete. Accordingly, to ensure reliable electricity supply to consumers from the Mukacheve 400/220/110/35 kV substation. reconstruction of 400 kV VRU, 220 kV VRU, 110 kV VRU, 35 kV VRU and 10 kV KTP
Budget869'940'002 UAH
Implementation period38 months