Reconstruction of the main pressure water supply pipeline between the village of Tverdomedovo and the village of Bila Krynytsia, Velykoleksandrivska settlement territorial community, Beryslav district, Kherson region
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The project involves the reconstruction of the main pressure water supply system between the village of Tverdomedove and the village of Bila Krynytsia of the Velikooleksandrivska settlement territorial community of the Beryslav district of the Kherson region. The implementation includes the replacement of worn sections of the water supply network using polyethylene pipes PE100 SDR11 with a diameter of 90 mm and 110 mm with a total length of 11.195 km, the installation of shut-off valves, the arrangement of water supply wells, as well as the construction of two water pressure towers of the Rozhnovsky type with a volume of 25 m³ each. The project is aimed at solving the problems of critical physical wear and tear of the existing water supply system, frequent accidents, water losses and unstable pressure in the network, which negatively affects the uninterrupted provision of the population with drinking water and fire-fighting needs. The expected results of the project implementation are to increase the reliability and continuity of centralized water supply, reduce accident rates and operating costs, ensure regulatory pressure in the network, improve sanitary and epidemiological living conditions for the population, and create conditions for the sustainable functioning of the community's engineering infrastructure.
The purpose of the project
Main goal:
Improving the condition of infrastructure
Secondary goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Population in the geographical area of influence of the project
803 human
Number of IDPs in the geographical area of impact of the project
95 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Development and Reconstruction of Subnational Infrastructure
Stream
Development and rehabilitation of municipal infrastructure of subnational governments
Strategic document
Стратегія розвитку територіальної громади
Task
1.1.2 Ensure the development of cultural and local heritage protection centers that form local self-awareness and bind residents to their places of residence
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Так, у прогнозі попиту враховано актуальні демографічні та економічні тенденції, оскільки проєктні рішення з реконструкції магістрального напірного водопроводу приймалися з урахуванням фактичного навантаження на інфраструктуру та очікуваних умов її експлуатації без збільшення розрахункової потужності.
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the main pressure water supply pipeline between the village of Tverdomedovo and the village of Bila Krynytsia, Velykoleksandrivska settlement territorial community, Beryslav district, Kherson region
Technical Solution 2
Current repairs and emergency restoration work on the existing main pressure water pipeline between the village of Tverdomedove and the village of Bila Krynytsia
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]