Modernization of the heating system infrastructure of the Storozhynetsk Lyceum of the Storozhynetsk City Council of the Chernivtsi district of the Chernivtsi region.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The flagship institution Storozhynetsky Lyceum of the Storozhynetsky City Council of the Chernivtsi district of the Chernivtsi region is one of the largest and key institutions of general secondary education in the community. The lyceum building has been in operation for many years and requires a comprehensive renovation of the infrastructure to ensure proper learning conditions and compliance with modern educational standards. The heating system and facade insulation are planned to be modernized in the premises of the institution, which will significantly increase energy efficiency, reduce heat loss and create comfortable conditions for students and staff. Carrying out such work is also important in the context of preparing the institution for the transition to the status of a specialized lyceum, in accordance with the requirements of the school education reform. Comprehensive modernization of the infrastructure will contribute to the long-term and effective operation of the building, improving the quality of the educational environment and ensuring safe, comfortable and modern learning conditions.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
35 human
Number of people who will use the service
832 human
Number of employees of the institution/institution/organization
150 human
Other functional
13 units
Other functional
35 units
Number of IDPs in the geographical area of impact of the project
35 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Modernization of the infrastructure of institutions and facilities of general secondary education
Strategic document
Стратегія розвитку територіальної громади
Task
3.4.1. Development of a network of educational and preschool institutions in the community
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Modernization of the heating system infrastructure of the Storozhynetsk Lyceum of the Storozhynetsk City Council of the Chernivtsi district of the Chernivtsi region.
Technical Solution 2
Installation of individual autonomous heating systems in the buildings of the Supporting Institution Storozhynetsky Lyceum
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]