General information
Description of the project
The project involves the reconstruction of the operating room of the surgical building of the KP "Hospital No. 2 named after V.P. Pavlusenko" of the Zhytomyr City Council. It is planned to redevelop the premises of the second floor in accordance with modern medical and technological requirements, modernize engineering systems (ventilation, power supply, medical gases), reconstruct the ventilation chamber, thermally renovate facades and increase the energy efficiency of the building, as well as equip the operating rooms with modern medical equipment. The expected results are the creation of a modern operating room with three functional operating rooms (scheduled, emergency, trauma); ensuring a high level of infection control and patient safety; improving the quality and accessibility of specialized surgical care to the community; improving the working conditions of medical personnel; reducing energy consumption and operating costs of the institution.
The purpose of the project
Main Goal:
Improving the quality of services
Secondary Goal:
Increasing compliance with modern standards, Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other functional
279 m2
Other functional
261 m2
Other functional
1034 m3
Other functional
322 m2
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities (specialized medical care)
Strategic document
Регіональна стратегія розвитку
Task
3.1.1. Modernizing the region's capable network of healthcare facilities and ensuring access to necessary medical services
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the operating block of the surgical building of the KP "Hospital No. 2 named after V.P. Pavlusenko" ZhMR at the address: Zhytomyr, st. R. Shukhevych, 2a
Technical Solution 2
Modernization of the operating room of the surgical building of the municipal enterprise "Hospital No. 2 named after V.P. Pavlusenko" to improve the quality and safety of medical services
[The technical approach was selected for further detailed analysis or implementation.]
[The project initiator has not taken any decision about this alternative technical approach.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]