Reconstruction of the basement extension of the building of the polyclinic No. 1 of the KNP "Kherson City Clinical Hospital named after O.S. Luchansky" of the Kherson City Council with the installation of a dual-purpose protective structure with the properties of a PRU at the address: Kherson city
Sector
Healthcare
Stream
Arrangement of civil defense protective structures (shelters) in healthcare facilities
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Investment Feasibility Study
Implementation
Completion
- Preparation
- General information
- Strategic Case
- Economic Case
- Financial Case
- Management Case
General information
Description of the project
KNP "Kherson City Clinical Hospital named after O.S. Luchansky" is a multi-profile, powerful healthcare institution, the structure of which consists of 12 separately located facilities, with a total area of 33,461.9 m2. The area of the hospital's land plot is 5.1373 hectares.
It is planned to reconstruct the basement with the construction of a dual-purpose hospital building, the project must provide all the necessary premises and ensure compliance with current regulatory documents. All premises must be designed taking into account their purpose, their location must be logical and convenient for patients and staff.
The purpose of the project
Main goal:
Creation of new facilities and services
Secondary goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Since the beginning of the Russian aggression against Ukraine, the city of Kherson has been constantly suffering from shelling by the Russian troops, civilians are constantly suffering, and therefore the safety of employees and patients within the hospital is currently one of the important functions, goals and objectives of a medical institution. The hospital needs
reconstruction of the basement with the installation of a dual-purpose building with the protective properties of an anti-radiation shelter.
Socio-economic context
Indicator
Value
Number of people who will use the service
91 human
Population in the geographical area of influence of the project
75360 human
Number of IDPs in the geographical area of impact of the project
23457 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Arrangement of civil defense protective structures (shelters) in healthcare facilities
Strategic document
State Strategy for Regional Development for 2021–2027
Task
36 Medical services
Project objectives
Indicator
Base value
Target value
Demand for the service and its dynamics
Indicator
Year
Demand
Annual demand for services/infrastructure
1
91 human
Economic justification
Alternative technical solutions
Technical Solution 1
Technical solution 2
Technical Solution 2
Technical solution 1
Total costs190'127'769 UAH32'720'000 UAH
Average annual costs800'000 UAH800'000 UAH
Project duration, incl.13 months8 months
Service life600 months600 months
Target indicatorsDefined Defined
Technical Solution Status
Active
Rejected
Financial justification
Total project budget
Total preliminary budget190'127'769 UAH32'720'000 UAH
Capital costs190'127'769 UAH32'720'000 UAH
Operational costs0 UAH0 UAH
Preliminary cost breakdown
Operating costs for implementation0 UAH0 UAH
For preparation1'388'872 UAH100'000 UAH
For implementation188'473'897 UAH30'000'000 UAH
For operation250'000 UAH420'000 UAH
For closing15'000 UAH2'200'000 UAH
Average project cost per service recipient
Service Unitоб'єкт будівництва
Service Unit Cost189'862'769 UAH
Profitability of the project
Is the project expected to generate income?
ResponseNoNo
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo