- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
During the full-scale invasion in 2022, bridges/overpasses in the Kyiv region were destroyed, which disrupted transport logistics and connections between cities and villages. Restoring transport logistics will allow logistics and transport connections to be restored and the economic situation to be improved. As part of cooperation with UKEF, a loan of EUR 30,794,329.74 was attracted from Citibank to co-finance the reconstruction of bridges in accordance with a defined list of 6 bridges in the Kyiv region.
The purpose of the project
Main Goal:
Rebuilding the damaged/destroyed
Secondary Goal:
Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Reducing territorial or social gaps, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other functional
100 %
Number of jobs, including for IDPs
200 human
Number of people who will use the service
250 thous. people
Other functional
10 %
Other functional
15 %
Strategic Case
Strategic feasibility of the project
Sector
Transport Sector
Subsector
Road transport and road infrastructure
Stream
Development and restoration of public road infrastructure
Strategic document
National Transport Strategy of Ukraine until 2030
Task
1 Ensuring the functional acceptability of the network of public roads through their restoration and development, taking into account the integration of the Ukrainian road network into the European one
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Bridge Installation (UKEF)
Technical Solution 2
A technical solution was considered, which involves refusing to restore damaged bridges and overpasses and leaving them in a destroyed state as artificial obstacles in the event of a repeated military offensive.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]