"Ukraine-EU Solidarity Lanes. Optimization and modernization of flows in terms of infrastructure capacity, interoperability and service efficiency at the main border crossing points with Poland/Ukraine"


Sector
Transport Sector
Stream
Development and restoration of public road infrastructure
Maturity level
60
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SPP
Implementation
Completion

General information

Description of the project

Creation and improvement of EU-Ukraine solidarity lanes by optimizing and modernizing transport flows in terms of infrastructure capacity, compatibility and efficiency of road connections at the main border crossing points between Poland and Ukraine

The purpose of the project

Main Goal:

Creation of new facilities and services

Description of the purpose of the project and ways to achieve it

Problems and solutions resulting from project implementation

Socio-economic context

Indicator

Value

Capacity

570 bag places

Strategic Case

Strategic feasibility of the project

Sector

Transport Sector

Subsector

Road transport and road infrastructure

Stream

Development and restoration of public road infrastructure

Strategic document

National Transport Strategy of Ukraine until 2030

Task

1 Ensuring the functional acceptability of the network of public roads through their restoration and development, taking into account the integration of the Ukrainian road network into the European one

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

умови пропускної здатності
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
40000 vehicles
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?

No
[Response was provided in the Investment Feasibility Study]

Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?

Conducting an EIA is not required.
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Were consultations held with representatives of target groups to take into account gender equality issues in the project?

No consultations were held with target groups.
[Response was provided in the Investment Feasibility Study]

Have the gender risks and social impacts of the project been assessed?

None of the options are applicable

Are there management and institutional mechanisms in place to ensure gender equality?

Not provided for by the project
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Gantt_Chart_Poland_Lviv_Service_03.08.23_for 26.6 million euros M-09 km183+260, M-10 km63+500 and 63+700.xlsx
15.08.2025
16:34:14 UTC

Alternative technical solutions

Technical Solution 1

Construction of parking lots for trucks at km 183+260 (right) and km 189+500 (right) Lviv region (Additional parking spaces for trucks at PP Rava-Ruska/Grebenneconstruction of parking lots for trucks at km 63+500 (right) and km 63+700 (left) Lviv region (Expansion of existing parking lot for trucks in Krakovka/Korchova)),

Technical Solution 2

construction of a service complex

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)1'334'908'244 UAH1'888'546'877 UAH
For preparation2'100'000 UAH6'000'000 UAH
For implementation1'332'808'244 UAH1'882'546'877 UAH
Project operation and closure cost5'050'000 UAH12'070'000 UAH
For operation5'000'000 UAH12'000'000 UAH
For closing50'000 UAH70'000 UAH
Average annual costs5'000'000 UAH0 UAH
Project duration, incl.48612 months48612 months
Deadline for developing a FFS24300 months24300 months
Implementation period24312 months24312 months
Service life600 months300 months
Target indicatorsDefined Not defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Pending

[The project initiator has not taken any decision about this alternative technical approach.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

What procurement strategy was chosen for the project implementation, and what justifies its feasibility in the context of the market and project objectives?
Згідно чинного законодавства

[Response was provided in the Investment Feasibility Study]

What approaches are planned to be used to ensure transparency, competition, and efficiency in the procurement process?
Згідно чинного законодавства

[Response was provided in the Investment Feasibility Study]

What types of procurement procedures are envisaged by the project (open tender, negotiated procedure, competitive dialogue, etc.)?
Open competitive bidding

[Response was provided in the Investment Feasibility Study]

Pre-market engagement
Згідно чинного законодавства

[Response was provided in the Investment Feasibility Study]

Potential market participants
Згідно чинного законодавства

[Response was provided in the Investment Feasibility Study]

Market readiness assessment
готовий

[Response was provided in the Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget1'339'958'244 UAH1'900'616'877 UAH
Project cost (preparation and implementation)1'334'908'244 UAH1'888'546'877 UAH
For preparation2'100'000 UAH6'000'000 UAH
For implementation1'332'808'244 UAH1'882'546'877 UAH
Project operation and closure cost5'050'000 UAH12'070'000 UAH
For operation5'000'000 UAH12'000'000 UAH
For closing50'000 UAH70'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitстояночне місце
Service Unit Cost2'835'762 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project management structure defined: working group, chair, project team?
Yes

[Response was provided in the Investment Feasibility Study]

What categories of experts and consultants have already been involved at the project preparation stage?
Specialists in interaction with international financial organizations (IFOs)

[Response was provided in the Investment Feasibility Study]

Financial consultants/modelers

[Response was provided in the Investment Feasibility Study]

Legal consultants

[Response was provided in the Investment Feasibility Study]

Commercial experts

[Response was provided in the Investment Feasibility Study]

Economic analysts

[Response was provided in the Investment Feasibility Study]

Strategic consultants

[Response was provided in the Investment Feasibility Study]

Technical experts

[Response was provided in the Investment Feasibility Study]

Management experts / project managers

[Response was provided in the Investment Feasibility Study]

Are there plans to involve experts and consultants for further implementation of the project?
No

[Response was provided in the Investment Feasibility Study]

Risk assessment

Political riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project require preparation assistance from Project Preparation Programs (PPF)?

None of the options are applicable

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable
Need for financing

Does the project require additional funding for preparation?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
16/08/2025SP-N-160825-045E741DState SPInvestment Feasibility StudyCancellation of the decision to include in a joint venture--
07/10/2025SP-N-071025-8B7CD115State SPInvestment Feasibility StudyInclude--
01/10/2025SPP-N-011025-9BF3ED5AState SPPInvestment Feasibility StudyNot approved--
28/10/2025SPP-N-281025-40425AB8State SPPInvestment Feasibility StudyInclude-60