State Single Project Pipeline

Within the Public Investment Management (PIM) reform being implemented by the Government of Ukraine, a unified approach to managing public investments is being introduced at the national, regional, and local levels. In particular, a legislative framework regulating PIM matters has been approved.

The procedure for forming the Single Project Pipeline (SPP) of public investments at the state, regional, and community levels is regulated by Cabinet of Ministers Resolution No. 527 of February 28, 2025. According to the procedure, the SPP contains a list of priority projects and programs from sectoral pipelines that have undergone expert appraisal and have been approved by the Strategic or Local Investment Council as eligible for the corresponding budget financing.

The formation of the SPP at state, regional and community levels through the DREAM ecosystem ensuring transparency and enabling review, analysis, and monitoring by sectoral ministries, international partners, IFIs, and the public. This enhances opportunities for attracting funding.

Information regarding projects and programs is displayed on the State Single Project Pipeline, in accordance with the decisions of the Strategic Investment Council, which are official and subject to mandatory use. At the same time, the public API of the system may temporarily display information that differs in certain particulars from the information published on the portal; such discrepancies are of a purely technical nature and shall be remedied in the prescribed manner.

Reform
CMU Resolution No. 527

All sectors
All streams
Project code
Keyword
Initiator
Project coverage area
Number of alternative technical approaches
Initiation date
Budget
Status
State level of SPP
State level of SP
Date10. 2025
SectorMunicipal infrastructure and services
SubsectorProtective Structures for Infrastructure Facilities
StatusInvestment Feasibility Study

Preparation of the project "Reconstruction of shipping locks with the installation of physical protection of critical infrastructure elements"

Project goal
Increasing compliance with modern standards. Introducing innovations and energy-efficient solutions
Geography
All Ukraine
Initiator
STATE ENTERPRISE OF WATERWAYS "UKRVODSHLYAH"
Preparation of the project "Reconstruction of shipping locks with the installation of physical protection of critical infrastructure elements"
Production of the project "Protection of shipping locks by means of electronic warfare"
Protection of shipping locks by installing physical protection (anti-drone net)
Budget7'510'002 UAH
Implementation period15 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Strengthening its own oil service function by updating the fleet of specialized equipment of JSC "Ukrnafta"

Project goal
Increasing compliance with modern standards. Increasing compliance with modern standards, Improving the quality of services
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Renewal of the specialized equipment fleet of JSC "Ukrnafta" through procurement
Procurement of services from external contractors for relevant work
Budget6'530'000'003 UAH
Implementation period30 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Purchase of KRS machines to increase the efficiency of capital repairs by our own forces and expand the operational well fund

Project goal
Capacity building. Increasing compliance with modern standards, Increasing compliance with modern standards, Creation of new facilities and services, Improving the quality of services
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Purchase of 30 new KRS machines (65 tons - 26 units, 125 tons - 4 units)
Procurement of services of an external contractor for conducting RRC
Increasing the efficiency and complexity of performing routine and capital repairs of wells, which is a necessary condition for implementing the Company's strategic goals of increasing oil and gas production.
Budget1'407'000'003 UAH
Implementation period24 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorOil and gas industry
StatusPreliminary Investment Feasibility Study

Purchase of gas pumping units for JSC "Ukrtransgaz" (3 gas pumping units with a capacity of 13 MW)

Project goal
Improving the condition of infrastructure. Increasing compliance with modern standards
Geography
All Ukraine
Initiator
JOINT STOCK COMPANY "UKRTRANSGAZ"
purchase of 3 HPA with a capacity of 13 MW
further use of existing equipment
The purchase of new gas storage units will ensure uninterrupted operation of the compressor shops of underground gas storage facilities and guaranteed gas withdrawal from the underground gas storage facilities at maximum productive levels, especially during critical periods.
Budget2'131'200'001,02 UAH
Implementation period27 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Construction of the 750 kV overhead line of the Zaporizhzhya NPP - Kakhovska

Project goal
Creation of new facilities and services.
Geography
All Ukraine
Initiator
PRIVATE JOINT STOCK COMPANY "NATIONAL ENERGY COMPANY "UKRENERGO"
Construction of the 750 kV overhead line of the Zaporizhzhya NPP - Kakhovska
Not provided
The main objective of the project "Construction of a 750 kV overhead line of Zaporizhia NPP - Kakhovka" (hereinafter referred to as the Project) is to increase the reliability of the southern operating modes of the Unified Power System of Ukraine by removing network restrictions on the output of the Zaporizhia NPP, stabilizing the voltage in the Southern and Crimean power systems (PS), and increasing the throughput capacity of the southern sections by strengthening the connection of the Kakhovka power node with the main networks of the Unified Power System of Ukraine.
Budget6'000'000'002 UAH
Implementation period180 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Installation of a gas-fired power plant up to 10 MW (Supporting critical distributed generation Stage II: capacity expansion in Poltava region)

Project goal
Creation of new facilities and services. Capacity building, Contribution to climate or environmental goals, Increasing compliance with modern standards, Increasing compliance with modern standards, Developing new territories or functions, Improving the equality of wealth distribution, Increasing the even distribution of resources, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation, Поява нових виробничих потужностей, Improving the quality of services, Reducing territorial or social gaps, Meeting demand
Geography
Poltavska region
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Construction of a modern gas-fired power plant with an installed capacity of up to 10 MW
Construction and commissioning of a solar power plant (SPP) with a capacity of 21 MW
Construction of a modern gas-fired power plant with an installed capacity of up to 10 MW based on the production capacities of a utility company in Poltava region. The plant will operate on natural gas and annually produce ≈40.9 GW·h of electricity for sale on the RDN during peak hours, provide auxiliary services to NPP «Ukrenergo», and also provide heat supply ≈11,153.7 Gcal/year for the needs of the community. GPM technology ensures quick starts/stops, operation in flexible modes, and effective balancing of RES.
Budget611'969'303 UAH
Implementation period18 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Installation of a gas-fired power plant up to 20 MW (Supporting critical distributed generation Stage IV: capacity expansion in Lviv region)

Project goal
Capacity building. Contribution to climate or environmental goals, Increasing compliance with modern standards, Increasing compliance with modern standards, Creation of new facilities and services, Developing new territories or functions, Improving the equality of wealth distribution, Increasing the even distribution of resources, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation, Поява нових виробничих потужностей, Improving the quality of services, Reducing territorial or social gaps, Meeting demand
Geography
Lvivska region
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Installation of a gas-fired power plant up to 20 MW (Supporting critical distributed generation)
Construction of a 41.5 MW solar power plant
The project involves the construction of a modern gas-fired power plant with an installed capacity of up to 20 MW on the territory of the production facilities of the utility in the Lviv region. The plant will operate on natural gas and annually produce about 81.8 GWh of electricity, which will be supplied to the day-ahead market (DAB) in peak load mode, as well as to provide auxiliary services to NPP Ukrenergo. The installation of gas-fired power plants will increase the flexibility and stability of the Unified Energy System of Ukraine, reduce dependence on unstable electricity supplies and ensure effective integration of renewable energy sources. Due to their technical characteristics, the gas-fired power plants are able to start and stop quickly, operate in variable modes, which makes them an optimal tool for balancing the power system. The implementation of the project will contribute to the development of regional infrastructure, the creation of new jobs, increased energy security, and sustainable socio-economic development of the Lviv region.
Budget1'337'840'600 UAH
Implementation period24 months
State level of SPP
State level of SP
Date10. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Installation of a gas-fired power plant up to 10 MW (Supporting critical distributed generation Stage III: capacity expansion in Cherkasy region)

Project goal
Creation of new facilities and services. Capacity building, Contribution to climate or environmental goals, Increasing compliance with modern standards, Increasing compliance with modern standards, Developing new territories or functions, Rebuilding the damaged/destroyed, Improving the equality of wealth distribution, Increasing the even distribution of resources, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation, Поява нових виробничих потужностей, Improving the quality of services, Reducing territorial or social gaps, Meeting demand
Geography
Cherkaska region
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Construction of a modern gas-fired power plant with an installed capacity of up to 10 MW
Construction and commissioning of a solar power plant (SPP) with a capacity of 21 MW
Construction of a modern gas-fired power plant with an installed capacity of up to 10 MW based on the production capacities of a utility company in Cherkasy region. The plant will operate on natural gas and annually produce ≈40.9 GW·h of electricity for sale on the RDN during peak hours, provide auxiliary services to NPP «Ukrenergo», and also provide heat supply ≈11,153.7 Gcal/year for the needs of the community. GPM technology ensures quick starts/stops, operation in flexible modes, and effective balancing of RES.
Budget612'063'431 UAH
Implementation period18 months
State level of SPP
State level of SP
Date09. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

New construction. Technological complex for the production of heat-generating assemblies

Project goal
Creation of new facilities and services. Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation, Поява нових виробничих потужностей
Geography
Yuzhnoukrainsk city
Initiator
JOINT STOCK COMPANY "NATIONAL ATOMIC POWER GENERATION COMPANY "ENERGOATOM"
New construction. Technological complex for the production of heat-generating assemblies
Purchasing nuclear fuel from foreign suppliers
Organizing nuclear fuel production will reduce the risks of providing Ukrainian nuclear power plants with nuclear fuel, ensure the development of domestic production, preserve and create new jobs, and increase revenues to budgets of all levels
Budget9'320'217'459,2 UAH
Implementation period60 months
State level of SPP
State level of SP
Date08. 2025
SectorEnergy Sector
SubsectorElectric power industry
StatusInvestment Feasibility Study

Installation of a gas-fired power plant with a capacity of up to 20 MW in the Cherkasy region (Supporting critically needed distributed generation)

Project goal
Creation of new facilities and services. Capacity building, Contribution to climate or environmental goals, Increasing compliance with modern standards, Increasing compliance with modern standards, Developing new territories or functions, Improving the equality of wealth distribution, Increasing the even distribution of resources, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation, Поява нових виробничих потужностей, Improving the quality of services, Meeting demand
Geography
Cherkaska region
Initiator
JOINT STOCK COMPANY "UKRNAFTA"
Installation of a gas-fired power plant with a capacity of up to 20 MW in the Cherkasy region (Supporting critically needed distributed generation)
Construction of a solar power plant with corresponding CAPEX costs.
Responding to the current challenges to the stability of the operation of the Unified Energy System of Ukraine (UES-U), JSC "Ukrnafta" made a strategic decision to focus on the production of electric and thermal energy using natural gas. A gas-piston plant is a generation system created on the basis of an internal combustion piston engine that runs on natural or other fuel. The project involves the installation of a complex of gas-piston plants with a total installed capacity of up to 20 MW on the territory of the production facilities of a utility in Cherkasy region, which will run on natural gas, in order to produce and supply electricity for sale on the "day-ahead market" (DAM) in peak load mode, and to provide auxiliary services to NPP "Ukrenergo". In addition to receiving additional profit, JSC "Ukrnafta" from the sale of electricity and/or the provision of auxiliary services, the project is designed to ensure the supply of an additional annual volume of thermal energy in the amount of ~ 22,307 Gcal for the territorial community, and electrical energy in the Unified Energy System-U in the amount of 82 GWh per year. In addition to the generation of electricity as such and ensuring the supply of additional heat supply, the feasibility of installing gas-piston plants is due to the growing need for balancing services in the Unified Energy System-U. Gas-piston plant technologies are best suited for flexible modes with frequent starts and stops and can therefore effectively cooperate with generating plants from renewable energy sources and provide system services. Thus, the gas-piston power plant will be able to provide the so-called auxiliary services for balancing the power system, in particular, during hours of no wind (for wind power plants) or sunlight (for solar power plants).
Budget1'401'253'000 UAH
Implementation period26 months