"Overhaul of the catering unit at the Municipal Institution "Lozov Lyceum No. 4" of the Lozov City Council of the Kharkiv Region at the address: Kharkiv Region, Lozov City, Microdistrict 4, Building 45"
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The premises subject to major repairs are located on the first floor of a four-story building of an educational institution. External enclosing structures - reinforced concrete wall panels 400 mm thick. Internal partitions - brick. Ceilings - reinforced concrete slab. The height of the premises is 2.98 m. The total area of the catering section is 436.35 m2. Parts of the building subject to major repairs - installation of internal and replacement of external water supply and drainage networks; - installation of supply (with heating from heat supply networks) and exhaust ventilation; - installation of electrical wiring, installation of lighting with backup power lamps; - installation of refrigeration and freezers for food storage.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of employees of the institution/institution/organization
51 human
Number of people who will use the service
344 human
Number of IDP users
12 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)
Strategic document
Strategy for Reforming the School Nutrition System until 2027
Task
2.1. Implementation of projects for the construction/renovation/modernization of catering units in secondary education institutions, based on a modern technological process that ensures compliance with standards based on the principles of the HACCP system, and the preparation of high-quality and safe food in an assortment
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of the catering unit "Loziv Lyceum No. 4"
Technical Solution 2
Reconstruction of the catering unit "Loziv Lyceum No. 4"
[The technical approach was selected for further detailed analysis or implementation.]
[The project initiator has not taken any decision about this alternative technical approach.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]