"Overhaul of the sewage pumping station and treatment facilities on the territory of the "Ploshchadka" residential area in the village of Hnizdychiv, Stryi district, Lviv region"


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Maturity level
81
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

On the territory of the residential area «Ploschadka» In the village of Hnizdychiv, Hnizdychiv Village Council, Stryi district, Lviv region, there is a sewage network that was put into operation in 1949 and includes a sewage pumping system consisting of networks and treatment tanks, and a sewage collector. Over the decades of operation, the engineering structures have suffered significant wear and tear, which has led to numerous problems with drainage. Today, the sewage network, which serves 360 residents of the specified area for the collection of liquid sewage, is in an emergency state. The existing sewage pumping station (SPS) does not provide sewage pumping. The structures designed to pump out sewage are not working, and liquid sewage, due to clogged pipelines, is drained into septic tanks manually. Thus, the sewage system in the residential area needs urgent modernization, including major repairs and the introduction of the latest technologies and energy-efficient equipment. This is necessary to ensure reliable drainage from the homes of 360 people and prevent environmental pollution.

THE PROJECT provides for:
- replacement of the central heating system (capacity 25 cubic meters)
- overhaul of the treatment facilities
- replacement of the route between the sewage treatment plant and the treatment facilities with a length of 158 m.
- installation of a biological treatment station
- replacement of the power supply system

Total project budget - 2918,204 thousand UAH
Work completion period - within 1 year

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Contribution to climate or environmental goals, Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the quality of services

Description of the purpose of the project and ways to achieve it

On the territory of the residential estate "Ploshchadka" of the village of Hnizdychiv, Hnizdychiv TG, Stryi district, Lviv region, at the address ul. 22 Januar, 16, there is a sewage network that was put into operation in 1949 and includes a sewage pumping system consisting of networks and treatment tanks, and a sewage collector. Over the decades of operation, the engineering structures have undergone significant wear and tear, which has led to numerous problems with drainage. Today, the sewage network, which serves 360 residents of the specified estate in the collection of liquid waste, is in a dilapidated state. The existing sewage pumping station (SPS) does not provide pumping of wastewater. The structures designed to pump wastewater are not working, and liquid waste, due to clogged pipelines, is drained into septic tanks manually. Thus, the drainage system in the residential area requires urgent modernization, including major repairs and the introduction of the latest technologies and energy-efficient equipment. This is necessary to ensure reliable drainage from the homes of 360 people and prevent environmental pollution. THE PROJECT provides for: - replacement of the sewage treatment plant (capacity 25 cubic meters) - major repairs of treatment facilities - replacement of the route between the sewage treatment plant and treatment facilities with a length of 158 m. - installation of a biological treatment station - replacement of the power supply system Total project budget - 2918,204 thousand UAH Work completion period - within 1 year

Problems and solutions resulting from project implementation

The drainage system in the residential area requires urgent modernization, including major repairs and the introduction of the latest technologies and energy-efficient equipment. This is necessary to ensure reliable drainage from the homes of 360 people and prevent environmental pollution. THE PROJECT provides for: - replacement of the sewage treatment plant (capacity 25 cubic meters) - major repairs of the treatment facilities - replacement of the route between the sewage treatment plant and the treatment facilities with a length of 158 m. - installation of a biological treatment station - replacement of the power supply system

Socio-economic context

Indicator

Value

Capital expenditure per year

2918 thous. UAH

Capacity

25 m3

Number of people who will use the service

360 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources

Strategic document

Регіональна стратегія розвитку

Task

3.1.2. Improving housing and communal infrastructure

Project objectives

Indicator
Base value
Target value
replacement of the route between the substation and the treatment plants
0 m
158 m

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

звернення мешканців житлового масиву та дані бухгалтерського обліку про амортизацію та стан зносу споруд
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
360 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
308_КД_ЗКР_5 (Summary estimate).xls
21.01.2026
12:46:48 UTC

Alternative technical solutions

Technical Solution 1

"Overhaul of the sewage pumping station and treatment facilities on the territory of the "Ploshchadka" residential area in the village of Hnizdychiv, Stryi district, Lviv region"

Technical Solution 2

"Construction of a sewage pumping station and treatment facilities on the territory of the "Ploshchadka" residential area in the village of Hnizdychiv, Stryi district, Lviv region"

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)2'918'204 UAH5'930'000 UAH
For preparation115'000 UAH130'000 UAH
For implementation2'803'204 UAH5'800'000 UAH
Project operation and closure cost65'000 UAH820'000 UAH
For operation50'000 UAH800'000 UAH
For closing15'000 UAH20'000 UAH
Average annual costs703'616 UAH0 UAH
Project duration, incl.14 months24318 months
Deadline for developing a FFS2 months6 months
Implementation period12 months24312 months
Service life300 months300 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget2'983'204 UAH6'750'000 UAH
Project cost (preparation and implementation)2'918'204 UAH5'930'000 UAH
For preparation115'000 UAH130'000 UAH
For implementation2'803'204 UAH5'800'000 UAH
Project operation and closure cost65'000 UAH820'000 UAH
For operation50'000 UAH800'000 UAH
For closing15'000 UAH20'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitвартість на обслуговування одного отримувача
Service Unit Cost8'286 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds115'000 UAH0 UAH
Expected Funds115'000 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Management rationale - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Is there an understanding of where to find relevant experts and consultants?
Yes, negotiations are already underway.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
21/01/2026SP-L-210126-0F0CFBC3Community SPInvestment Feasibility StudyIncludeStrategic fit confirmed-
30/01/2026SPP-L-300126-B75B7C5DCommunity SPPInvestment Feasibility StudyInclude-81