"Overhaul of the sewage pumping station and treatment facilities on the territory of the "Ploshchadka" residential area in the village of Hnizdychiv, Stryi district, Lviv region"
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
On the territory of the residential area «Ploschadka» In the village of Hnizdychiv, Hnizdychiv Village Council, Stryi district, Lviv region, there is a sewage network that was put into operation in 1949 and includes a sewage pumping system consisting of networks and treatment tanks, and a sewage collector. Over the decades of operation, the engineering structures have suffered significant wear and tear, which has led to numerous problems with drainage. Today, the sewage network, which serves 360 residents of the specified area for the collection of liquid sewage, is in an emergency state. The existing sewage pumping station (SPS) does not provide sewage pumping. The structures designed to pump out sewage are not working, and liquid sewage, due to clogged pipelines, is drained into septic tanks manually. Thus, the sewage system in the residential area needs urgent modernization, including major repairs and the introduction of the latest technologies and energy-efficient equipment. This is necessary to ensure reliable drainage from the homes of 360 people and prevent environmental pollution.
THE PROJECT provides for:
- replacement of the central heating system (capacity 25 cubic meters)
- overhaul of the treatment facilities
- replacement of the route between the sewage treatment plant and the treatment facilities with a length of 158 m.
- installation of a biological treatment station
- replacement of the power supply system
Total project budget - 2918,204 thousand UAH
Work completion period - within 1 year
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Contribution to climate or environmental goals, Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capital expenditure per year
2918 thous. UAH
Capacity
25 m3
Number of people who will use the service
360 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Регіональна стратегія розвитку
Task
3.1.2. Improving housing and communal infrastructure
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
"Overhaul of the sewage pumping station and treatment facilities on the territory of the "Ploshchadka" residential area in the village of Hnizdychiv, Stryi district, Lviv region"
Technical Solution 2
"Construction of a sewage pumping station and treatment facilities on the territory of the "Ploshchadka" residential area in the village of Hnizdychiv, Stryi district, Lviv region"
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]