Major renovation of the additional entrance, taking into account the needs of low-mobility groups of the population, of the building of the district administration of the Zaporizhia City Council on Builders' Boulevard, 19, Zaporizhia
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
In accordance with Article 40 of the Constitution of Ukraine, all citizens have the right (regardless of their physical capabilities) to personally address state authorities, local self-government bodies, and officials and employees of these bodies. However, many buildings, including district administrations, were built without taking into account the needs of persons with disabilities and other low-mobility population groups. Barrier-free access to the district administration building for low-mobility population groups will be ensured by major repairs to the additional/reserve entrance of the district administration with the installation of a ramp for persons with disabilities. Among other services that residents turn to, the district administration building houses the voter registry department, where applicants, including persons with disabilities, apply to clarify/make changes to personal data in the voter registry, clarify their electoral address. Internally displaced persons apply with requests for information from the State Voter Registry. Also, during the period of local elections, the Territorial Election Commission is located in the district administration building. In order to comply with the requirements of the Electoral Code regarding the accessibility of polling stations, persons with disabilities and other low-mobility population groups, and not to restrict the rights of citizens in ensuring the exercise of the right to vote, the building must be equipped with a ramp. Given the above, there is an urgent need to carry out a major overhaul of the additional entrance to the district administration building with the installation of a ramp, during which it is planned to install a ramp, equip the entrance to the building, a toilet on the first floor, doors to offices, creating appropriate conditions for access to the district administration and the ability to move around the district administration building for disabled people and other low-mobility population groups.
In order to implement this project in 2025, design and estimate documentation for the object ’Major repairs of the additional entrance taking into account the needs of low-mobility groups of the building of the district administration of the Zaporizhia City Council on Budivelnykiv Boulevard, 19, Zaporizhia» (hereinafter referred to as the Object). The next stage is the implementation of major repairs, the expected cost of which is 399,622.18 UAH (excluding the cost of work paid in 2025 for the production of design and estimate documentation). It is advisable to carry out the work in the near future, because in subsequent years the cost of work on the object will increase due to the increase in prices for building materials, work, and additional costs for recalculating design and estimate documentation.
Implementation of this The project and completion of work on the Facility will allow for unhindered access to the district administration building for low-mobility population groups, and the resolution of their urgent issues within the powers of the district administration.
The purpose of the project
Main goal:
Ensuring inclusiveness and equal opportunities
Secondary goal:
Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of users from low-mobility population groups
12550 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Creation of barrier-free routes in populated areas
Strategic document
Стратегія розвитку територіальної громади
Task
1.2. Creating conditions for increased well-being, comfortable and safe living for residents
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
не пов’язано
не пов’язано зі зміною клімату
не пов’язано
не пов’язано з використанням та захистом водних і морських ресурсів
не пов’язано
не пов’язано зі зміною клімату
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
construction work on the object "Overhaul of the additional entrance taking into account the needs of low-mobility groups of the building of the district administration of the Zaporizhia City Council on Builders' Boulevard, 19, Zaporizhia"
Technical Solution 2
current renovation of an additional entrance to the district administration building
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Оскільки обсяг робіт з капітального ремонту невиликий, вартість складає до 400 тис.грн, що є привабливим для малих та середніх підприємства м.Запоріжжя, які можуть бути потенціними виконавцями робіт
[Response was provided in the Investment Feasibility Study]
Вартість проєкту не є достатньою для залучення міжнародних підрядників. Потенційні виконавці - підприємства, розташовані в м.Запоріжжя
[Response was provided in the Investment Feasibility Study]
За результатми аналізу для досягнення поствалених завдань доцільно здійснити капітальний ремонт додаткового входу будівлі районної адміністрації
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]