Reconstruction of the boiler room with the installation of a cogeneration gas piston unit at the address: Mykola Rudenka St., 67 in the city of Dnipro.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the installation of a containerized gas-fired cogeneration plant (CPP) with a nominal electrical capacity of 2.3 MW.
The purpose of the project
Main Goal:
Improving the quality of services
Secondary Goal:
Increasing the even distribution of resources
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
14500 human
Capacity
2300 kW
Number of employees of the institution/institution/organization
20 human
Number of IDPs in the geographical area of impact of the project
1000 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Development and Reconstruction of Subnational Infrastructure
Stream
Development and rehabilitation of municipal infrastructure of subnational bodies
Strategic document
Стратегія розвитку територіальної громади
Task
A.4 Dnipro - a hub of new industries
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the boiler room with the installation of a cogeneration gas piston unit at the address: Mykola Rudenka St., 67 in the city of Dnipro.
Technical Solution 2
Reconstruction of the boiler room with the installation of a solar power plant (SPP) and storage tanks at the address: Mykola Rudenka St., 67 in the city of Dnipro.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]