Reconstruction of an administrative building for a center for providing administrative services in the "Transparent Office" format at the address: Dnipro, Mykhailo Hrushevskoho St., 70
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The reconstruction of the building is planned to adapt the existing administrative building to provide services to the population, bringing the premises to a satisfactory condition to improve operational properties using modern building materials and technologies. The detailed design provides for redevelopment of the premises, internal and external finishing works, replacement of the roof, replacement of windows and doors, insulation of the facade, adaptation of the building for unhindered access for persons with disabilities and other low-mobility groups (hereinafter - MGN), repair of porches, provision of the premises with the necessary engineering systems, equipping with technological equipment and furniture.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
95000 human
Number of employees of the institution/institution/organization
240 human
Number of IDP users
10000 human
Number of users from low-mobility population groups
500 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Development and Reconstruction of Subnational Infrastructure
Stream
Development and rehabilitation of municipal infrastructure of subnational governments
Strategic document
State Strategy for Regional Development for 2021–2027
Task
Task 2 Implementation of priority measures for the safety of life, restoration and stimulation of economic activity in territorial communities
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Reconstruction of an administrative building for a center for providing administrative services in the "Transparent Office" format at the address: Dnipro, Mykhailo Hrushevskoho St., 70
Technical Solution 2
Current (partial) renovation of the administrative building
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]