General information
Description of the project
3522 people live in the village of Ropcha of the Storozhynets urban territorial community. This populated area is quite large. The village is located 7 km. from the administrative center of the community - the city of Storozhynets and 30 km. from the regional and district center - the city of Chernivtsi. The Ropcha Lyceum named after «Štefan cel Mare shi Sfint» operates on the territory of the village of Ropcha, where 327 students study and the «Giochel» preschool educational institution, where 60 children are educated, therefore the presence of all vital and socially important facilities that ensure the vital activity of the settlement is absolutely necessary. As is known, physical culture, physical education and sports are important factors in the health of the population, disease prevention and organization of meaningful leisure. However, in the conditions of information and technological development, people often lead a relatively calm lifestyle. Of particular concern recently is the deterioration of the health of children and adolescents, more than 80% of whom, according to operational data of the KNP "Storozhynetska BLIL", have health abnormalities, more than 50% have an unsatisfactory state of physical development. Unfortunately, diseases typical of people of mature age are progressing in the younger generation. The desire of residents of the village of Ropcha to engage in sports is hampered by the lack of proper conditions and modernly equipped facilities for physical culture and sports. At the same time, in the communal property of the Storozhynets City Council on M. Eminescu Street there is a vacant plot (cadastral number 7324588000:02:002:1001), on which a sports ground with artificial turf can be placed, where not only school and kindergarten students, but also everyone who wants to, could engage in physical culture during extracurricular hours. The construction of the sports ground will contribute to the development of modern infrastructure in the field of sports, the formation of a healthy lifestyle, improving the health of community residents and increasing the level of living comfort in the territory of the village of Ropcha.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
2 human
Number of people who will use the service
327 human
Population in the geographical area of influence of the project
3522 human
Number of IDPs in the geographical area of impact of the project
4 human
Strategic Case
Strategic feasibility of the project
Sector
Sports and physical activities
Subsector
Sports and physical activities
Stream
Modernization and expansion of the sports infrastructure network
Strategic document
Стратегія розвитку територіальної громади
Task
3.6.2. Modernization and expansion of the sports infrastructure network
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Construction of a sports field with artificial turf on M. Eminescu Street in the village of Ropcha, Chernivtsi district, Chernivtsi region
Technical Solution 2
"Construction of a sports ground with natural grass (rolled lawn) in the village of Ropcha, Chernivtsi district, Chernivtsi region"
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]