The project to improve the efficiency of electricity transmission (modernization of substations)


Sector
Energy Sector
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State Single Project Pipeline
Implementation
Completion

General information

Description of the project

The project is implemented within the framework of: Agreement between the Cabinet of Ministers of Ukraine and the Government of Germany on Financial Cooperation (appropriations for 2006 and 2007), signed on 12/30/2011, ratified on 10/02/2012 (Law No. 5298-VI), entered into force on 12/04/2012; Credit Agreement between the Cabinet of Ministers of Ukraine and the Credit Institution for Reconstruction (KfW), signed on 12/30/2011, entered into force on 12/04/2012; - Separate Agreement between NPC «Ukrenergo» and KfW, signed on 12/30/2011. On 04/22/2024, Additional Agreement No. 2 dated 12/19/2022 was signed to the Separate Agreement between Ukrenergo and KfW dated 12/30/2011 to the Loan Agreement between the Cabinet of Ministers of Ukraine and KfW dated 12/30/2011 Modern requirements for ensuring the reliability of electrical networks in normal modes and modes of technological disruptions, relevant plans for further integration of the Unified Power System of Ukraine with the European energy system impose high requirements for the reliability of electrical equipment, which entails the need to carry out large-scale work on the comprehensive reconstruction of the electrical networks of the Unified Power System of Ukraine, an important component of which are electrical substations. The project envisages the reconstruction of two substations of the Dniprovska ES (330 kV substation "Kryvorizka" and 330 kV "Dnipro-Donbas" with the implementation of automated process control systems (APCS) at these substations. The project is aimed at ensuring reliable and uninterrupted operation of the electrical networks of the Unified State Electric Power System of Ukraine. To achieve the set goals, it is necessary to modernize the nodal substations of the power transmission network in order to ensure the necessary electrical connections and the level of electricity consumption. At the stage of Project implementation, changes were made to the direction of activity under the Project, namely: -    procurement and installation of physical protection measures for substations; - procurement and installation of autotransformers, single-phase reactors and related equipment for substations (damaged as a result of hostilities) from the entire Unified State Electric Power System network. 

The purpose of the project

Main goal:

Improving the condition of infrastructure

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The aim of the Project is to ensure a high level (stabilization) of electricity transmission and increase energy efficiency in Ukraine, which, in turn, will contribute to stimulating economic growth and sustainable improvement of living conditions of the population. The main objectives of the Project are to increase the level of safety, reliability and efficiency of electricity transmission by rehabilitating substations that have been in operation for a long time and have, for the most part, electrical equipment that has largely exhausted its operational life, guaranteed by the manufacturer. To achieve the set goals, it is necessary to modernize the nodal substations of the power transmission network in order to ensure the necessary electrical connections and the level of electricity consumption. The project provides for the reconstruction of two substations of the Dniprovska ES (330 kV substation "Kryvorizka" and 330 kV substation "Dnipro-Donbas") with the introduction of automated process control systems (ASKTP) at these substations.

Problems and solutions resulting from project implementation

reconstruction of two substations of the Dniprovska ES (330 kV substation "Kryvorizka" and 330 kV substation "Dnipro-Donbas") with the introduction of automated process control systems (APCS) at these substations

Socio-economic context

Indicator

Value

Other economic

1 UAH

Strategic Case

Strategic feasibility of the project

Sector

Energy Sector

Subsector

Electric power industry

Stream

Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)

Strategic document

Energy Strategy of Ukraine until 2050

Task

null Ensuring a stable, balanced model of operation of the Unified Power System of Ukraine; restoration, development and transformation of the power system, its sustainable operation;; increasing the efficiency of substations

Project objectives

Indicator
Base value
Target value

Demand for the service and its dynamics

Indicator
Year
Demand
Annual demand for services/infrastructure
1
1 UAH
Economic justification

Alternative technical solutions

Technical Solution 1

The project to improve the efficiency of electricity transmission (modernization of substations)

Technical Solution 2

not provided

Total costs1'951'852'953 UAH4 UAH
  • For preparation
  • 1 UAH1 UAH
  • For implementation
  • 1'951'852'950 UAH1 UAH
  • For operation
  • 1 UAH1 UAH
  • For closing
  • 1 UAH1 UAH
    Average annual costs1 UAH1 UAH
    Project duration, incl.204 months2 months
  • Deadline for developing a FFS
  • 60 months1 month
  • Implementation period
  • 144 months1 month
    Service life600 months1 month
    Target indicatorsDefined Not defined
    Components of a technical solution
    To components
    0
    To components
    0

    Financial justification

    Total project budget

    Total preliminary budget1'951'852'953 UAH4 UAH
    Capital costs1'951'852'953 UAH4 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation1 UAH1 UAH
    For implementation1'951'852'950 UAH1 UAH
    For operation1 UAH1 UAH
    For closing1 UAH1 UAH

    Average project cost per service recipient

    Service Unitне передбачено
    Service Unit Cost1 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH
    Management Rationale

    Risk assessment

    Political riskDefinedUndefined

    Organizational events

    ResponseDefinedUndefined
    Results of the feasibility analysis
    Economic Analysis
    Social benefits and costs
    not defined
    Environmental benefits and costs
    not defined
    Indirect benefits and costs
    not defined