Description of the project
The project involves the construction of an onshore wind power plant with an installed capacity of 297 MW in Vinnytsia region (on the territory of Pohrebyshchyna territorial community).
The implementation of the project is due to the relevance and need for the development of distributed generation in the regions of Ukraine (decentralization of generation) in order to ensure the stability of the energy system and energy independence, avoid the risks of power supply interruptions and cover the deficit in the energy system of Ukraine.
It is expected that the implementation of the project will have a positive impact on the development of decarbonization processes of operational activities, increase the share of electricity generated from renewable energy sources, reduce dependence on fossil fuels, and contribute to savings / reduction of greenhouse gas emissions.
The purpose of the project
Main Goal:
Поява нових виробничих потужностей
Secondary Goal:
Contribution to climate or environmental goals
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Operating expenses per year
929 mln UAH
Population in the geographical area of influence of the project
32.9 mln people
Number of IDPs in the geographical area of impact of the project
4601.1 thous. people
Other social
100 %
Strategic Case
Strategic feasibility of the project
Sector
Energy Sector
Subsector
Renewable energy and alternative fuels
Stream
Construction of wind power plants
Strategic document
National Energy and Climate Plan until 2030
Task
Development of wind energy, ensuring the stability of the unified power system of Ukraine
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Alternative solution 1 using wind turbines with lower unit capacity
Technical Solution 2
Alternative solution 2 using wind turbines with higher unit capacity
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]