"Creation of a modern educational space in the Dnipro Scientific Lyceum of Information Technologies of the Dnipro City Council within the framework of the implementation of the reform of the senior specialized school"
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The creation of modern laboratories for chemistry, biology, physics, robotics, a mathematics classroom and a STEM laboratory in the Dnipro Scientific Lyceum of Information Technologies of the Dnipro City Council is a strategically necessary step to ensure high-quality specialized secondary education and the development of the scientific and research potential of students. The relevance of the project is due not only to general changes in the system of the senior specialized school, but also to the specifics of the institution itself. The Dnipro Scientific Lyceum of Information Technologies is a scientific and specialized educational institution, the activities of which are aimed at identifying, developing and supporting capable and gifted students, organizing their research, project and innovation activities. Under such conditions, a modern subject and laboratory environment is not an additional advantage, but a mandatory institutional basis for the implementation of the educational program of the lyceum, in particular in the mathematical and natural sciences, physical and technological and interdisciplinary STEM areas.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Increasing compliance with modern standards, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
360 human
Number of employees of the institution/institution/organization
22 human
Other functional
200 human
Number of IDP users
21 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Providing general and secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Strategic document
National Strategy for Building a Safe and Healthy Educational Environment in the New Ukrainian School
Task
- creating a modern educational environment that will provide the necessary conditions, means and technologies for teaching students, teachers and parents
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
"Creation of a modern educational space in the Dnipro Scientific Lyceum of Information Technologies of the Dnipro City Council within the framework of the implementation of the reform of the senior specialized school"
Technical Solution 2
Purchase of multimedia equipment and electronic educational resources to create appropriate conditions for organizing the educational process
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]