"Repair (restoration) of the premises of the building of the Municipal Cultural Institution "Dnipro Art Museum" of the Dnipro City Council at the address: Dnipro, Shevchenko St., 21" (development of design and estimate documentation, including correction of design and estimate documentation, reconstruction work)
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
Repair (restoration) of the premises of the building of the Municipal Cultural Institution "Dnipro Art Museum" of the Dnipro City Council at the address: Dnipro, Shevchenko St., 21, namely: restoration of architectural decor (stucco moldings), plastering and painting works (2156 m); replacement of drains; replacement of the hard roof (roof of the building); replacement of dormer windows (attic) of the building; replacement of the windows of the building (95 windows, window size 240x120 cm); replacement of the blind area around the building (122 m); restoration of the entrance door to the building (320x205 cm); reconstruction of the granite surface of the central staircase (42 m).
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
1 thous. people
Number of people who will use the service
13 thous. people
Capacity
500 human
Number of employees of the institution/institution/organization
27 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
Extracurricular education
Stream
Network of centers for making up for educational losses
Strategic document
Strategic Action Plan of the Ministry of Education and Science of Ukraine until 2027
Task
3.1.1.2, 3.1.2.1, 3.2.1.2 of the direction "Every child in Ukraine has the opportunity to form a national identity, develop talents and abilities in the system of extracurricular education" Providing out-of-school education institutions with access to innovative tools and teaching methods in accordance with best international practices. Implementation of STEM education, entrepreneurship education, military-patriotic education and education for sustainable development and recovery. Creation of a network of out-of-school education institutions and its structural1 units at the community level.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
"Repair (restoration) of the premises of the building of the Municipal Cultural Institution "Dnipro Art Museum" of the Dnipro City Council at the address: Dnipro, Shevchenko St., 21" (development of design and estimate documentation, including correction of design and estimate documentation, reconstruction work)
Technical Solution 2
New construction of a building for the Municipal Cultural Institution "Dnipro Art Museum" of the Dnipro City Council, at the address: Dnipro, Shevchenko St., 21
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]