Overhaul of the sports hall of the Kulykiv Lyceum of the Kulykiv Settlement Council of the Chernihiv District, Chernihiv Oblast on St. Shevchenko, 4, in the village of Kulikivka
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The major renovation of the sports hall at the Kulykiv Lyceum includes a complete renovation of the main structural elements and infrastructure to ensure safe and modern conditions for physical education and sports. The main works include:
Floor renovation: installation of new sports surfaces that meet the safety and comfort requirements for various sports.
Wall and ceiling renovation: plastering, painting, installation of new lighting fixtures to ensure high-quality lighting in the hall.
Replacement of windows and doors: installation of energy-efficient windows and doors to preserve heat and provide natural lighting.
Appropriation of locker rooms and bathrooms: modernization or installation of new amenities for students and coaches.
Ventilation and heating system: installation or upgrade of systems to ensure a comfortable temperature regime and fresh air in the hall.
Equipment of the gym: supply and installation of modern sports equipment and equipment for various types of physical exercises and competitions.
This renovation will contribute to the creation of safe, comfortable and modern conditions for practicing sports, which is an important element of a healthy lifestyle and harmonious development of students. Lyceum.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Ensuring inclusiveness and equal opportunities
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of users from low-mobility population groups
9 human
Number of IDP users
21 human
Number of people who will use the service
916 human
Number of IDPs in the geographical area of impact of the project
198 human
Population in the geographical area of influence of the project
14116 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Unhindered access to quality education
Strategic document
Стратегія розвитку територіальної громади
Task
3.2.2 Improving the material and technical base of educational institutions
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Gym renovation
Technical Solution 2
Cosmetic renovation of the gym
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]