Reconstruction of the medical building 1 of the STATE NON-COMMERCIAL ENTERPRISE "ALL-UKRAINIAN MEDICAL AND REHABILITATION CENTER "Tsibli"" at the address: Kyiv region, Boryspil district, village of Tsibli, 2 Lisova st.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The purpose of the project is to develop solutions for the reconstruction of the existing medical building 1 – a modern medical center to provide high-quality, affordable, round-the-clock inpatient specialized medical and rehabilitation care to military personnel and war veterans of Ukraine, taking into account modern requirements for ensuring patient safety. The reconstruction involves the installation of a protective structure – anti-radiation shelter of group P-4 (hereinafter – PRU) for accommodation of 229 people.
The design solutions provide for modern medical equipment that meets modern requirements, including for laboratory research – biochemical, hematological automatic
analyzers, glucose and lactate analyzer, enzyme-linked immunosorbent analyzer, microscopes and centrifuges; in endoscopy for diagnostics – endoscopic system with monitor, video bronchoscope; for diagnostics – ultrasonic diagnostic systems, medical diagnostic telemetry complex, Holter measurement system, visiograph, diagnostic audiometer, autoreflectometer, dioptrimeter, etc. Ceiling-mounted anesthesia and surgical consoles are planned in the operating room; in the intensive care unit – wall consoles with medical gas supply, electricity supply, low-current systems, as well as an anesthesia station, aspirator, ventilator, patient condition monitoring information system, personal computers with the arrangement of the entire institution's computer network. The reconstruction of the medical building 1 is planned in one turn without division into start-up
complexes with stopping the medical process.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Ensuring inclusiveness and equal opportunities, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
138 bed-days
Number of users from low-mobility population groups
138 human
Number of jobs, including for IDPs
91 workplaces
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities
Strategic document
Strategy for the Development of the Healthcare System until 2030
Task
Strategic goal 1 Ensuring universal access of the population to quality medical services and tools for implementing the right to health
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the medical building
Technical Solution 2
Construction of a new medical building
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]