Energy saving measures. Reconstruction of the boiler room and connection to engineering networks at the address: Televiziyna Street, 3n, Kryvyi Rih, Dnipropetrovsk region


Sector
Municipal infrastructure and services
Stream
Development and rehabilitation of municipal infrastructure of subnational governments
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The construction of the boiler house is aimed at solving key problems that arise in the process of energy supply. The main objectives of the project are:

Ensuring energy security:

Increasing the level of energy independence of the region from external energy suppliers.

Improving energy efficiency: Using more efficient boilers and energy supply systems with low heat losses.

Environmental responsibility: Reducing emissions of harmful substances (CO2, NOx, SO2) by using modern gas purification technologies. 

Reducing energy supply costs: Creating an internal heat source will reduce dependence on external energy suppliers and reduce energy purchase costs. 

Strategic advantages of building a boiler house: 1. Energy efficiency and reliability:   The capacity of the boiler house allows to cover significant needs in thermal energy for both industrial facilities and residential complexes of the heating district.    The use of highly efficient technologies reduces fuel costs and increases the reliability of heat supply. 2. Flexibility in fuel use:   The boiler house can be designed to operate on different types of fuel: natural gas, diesel fuel, which makes it possible to adapt to changes in the energy market and ensure energy security.    3. Economic feasibility:   The cost of building a boiler house can be compensated by reducing the cost of purchasing energy and reducing the cost of servicing outdated facilities.  Increasing the efficiency of energy use will reduce the total costs of an enterprise or local community for thermal energy. 4. Innovation and technological development:    The introduction of modern boiler technologies (for example, cogeneration plants) can ensure not only the production of heat, but also electricity, which increases overall efficiency and reduces costs. 

The purpose of the project

Main goal:

Improving the quality of services

Secondary goal:

Contribution to climate or environmental goals, Increasing compliance with modern standards, Increasing compliance with modern standards, Creation of new facilities and services, Improving the equality of wealth distribution, Increasing the even distribution of resources, Introducing innovations and energy-efficient solutions, Meeting demand

Description of the purpose of the project and ways to achieve it

The purpose of the public investment project is to create a modern, energy-efficient and environmentally friendly source of thermal energy by building a new boiler house on the site of the decommissioned Mekhanobchormet boiler house, which will ensure reliable, economically justified and uninterrupted heat supply to consumers of the Kryvyi Rih heating district. Ensuring sustainable, efficient and environmentally friendly heat supply for an enterprise or region, taking into account the requirements for energy security, economic efficiency and environmental responsibility. The implementation of this project will allow increasing energy independence, reducing energy costs and promoting sustainable development. Reducing fuel consumption (natural gas, electricity and water through the installation of new energy-efficient equipment; reducing emissions of harmful gases into the atmosphere; providing the consumer with uninterrupted and high-quality thermal energy services). ensuring compliance with modern environmental standards; forming a reserve of capacities for the future development of urban infrastructure. Increasing the level of energy security and independence of the territorial community; reduction of technological and financial losses in the heat supply system;

Problems and solutions resulting from project implementation

1.1. Lack of a modern and reliable source of heat supply 1. Inefficient operation of boiler equipment The operation of the boiler room is characterized by extremely low energy efficiency, which is due to: physical and moral wear and tear of boiler equipment; unsatisfactory technical condition of boilers; limited opportunities for optimal regulation of operating modes. As a result, the actual load of boilers, according to the regime maps, does not exceed 40% of the nominal capacity, which leads to: fuel overconsumption; increase in the specific cost of thermal energy; decrease in the reliability of heat supply. 2. Lack of a chemical water treatment system The boiler room does not have a full-fledged chemical water treatment system, which negatively affects: the technical condition of boilers; durability of heating networks; stability of thermal hydraulic modes. The use of untreated or insufficiently prepared water leads to: scale formation and corrosion; reduction in boiler heat output; accelerated wear of equipment and pipelines; increased system failure rate. 3. Critical condition of district heating networks The district heating network, served by the KMK boiler house, is outdated and is in critical technical condition. Main problems: a significant part of the thermal insulation is made of mineral wool or slag wool, wrapped with: boehmite, foil insulation, roofing felt, in some places - shingles and waterproof canvas; thermal insulation materials have lost their properties or are completely destroyed; more than 70% of heating networks are worn out and require replacement or major reconstruction. This condition of the networks leads to significant heat losses and frequent accidents. 4. High level of accidents and interruptions in heat supply wear and tear of pipelines causes a constant trend towards an increase in the number of surges in heat networks. For the period from December 2023 to January 20, 2025: 219 heat supply outages were recorded; the total duration of outages was 20,626 hours. This leads to: systematic interruptions in heat supply to consumers; social tension; increased costs for emergency repairs; reduced trust in the district heating system. 5. Significant losses of thermal energy in networks The unsatisfactory condition of heating networks causes significant losses of thermal energy during transportation: 2022 - 37,274 Gcal 2023 - 32,820 Gcal 2024 - 37,356 Gcal Such losses indicate: irrational use of fuel and energy resources; a significant increase in heat production costs; the need for urgent systemic changes in heat supply. General assessment The combination of the above factors indicates that the further operation of the KMK boiler house and the associated heating networks without comprehensive modernization or replacement of the heat source is technically, economically and socially inexpedient. It is these circumstances that form a justified need for the implementation of a public investment project to build a new modern boiler house as an alternative and reliable source of heat supply.

Socio-economic context

Indicator

Value

Other economic

25 year

Other economic

485801 GJ

Other economic

870.5 m2

Other economic

195152 t

Other economic

1882 h

Number of people who will use the service

34769 human

Number of employees of the institution/institution/organization

13 human

Number of jobs, including for IDPs

13 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Development and Reconstruction of Subnational Infrastructure

Stream

Development and rehabilitation of municipal infrastructure of subnational governments

Strategic document

Стратегія розвитку територіальної громади

Task

1.5.2; 4.4.1; 3.4.4; 1.4.2; 4.5.1. Formation of a capable network of healthcare institutions of all levels (including the creation of rehabilitation departments); Elimination of the consequences of the Kakhovka HPP dam explosion; Creation and development of investment / innovation projects / products; Development of innovation laboratories / incubators; Development and improvement of the street and road network of the Kryvyi Rih Metropolitan Municipality with barrier-free access

Project objectives

Indicator
Base value
Target value
Annual water consumption
405333.76 m3
194872 m3
Annual consumption of natural gas for thermal energy production
15564.19 m3
14513.75 m3
Annual electricity consumption
733035.96 kWh
527364 kWh

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Підприємство КПТМ "Криворіжтепломережа" є монополістами у наданні послуг. Беруться історичні дані споживання.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
194872 m3
Annual demand for services/infrastructure
1
5273640 kWh
Annual demand for services/infrastructure
1
20667000 t
Annual demand for services/infrastructure
1
18276000 m3
Annual demand for services/infrastructure
1
34769 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?

Yes
[Response was provided in the Investment Feasibility Study]

Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?

Yes, it was conducted
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Were consultations held with representatives of target groups to take into account gender equality issues in the project?

No consultations were held with target groups.
[Response was provided in the Investment Feasibility Study]

Have the gender risks and social impacts of the project been assessed?

None of the options are applicable

Are there management and institutional mechanisms in place to ensure gender equality?

Not provided for by the project
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Calculations_for_entering_TV_1.xlsx
10.02.2026
10:59:05 UTC
ex01_5772-5354-3844-3884_20260204031447_raster_compressed.pdf
10.02.2026
10:59:13 UTC
20CD (OUTPUT).xls
10.02.2026
10:59:17 UTC

Alternative technical solutions

Technical Solution 1

Energy saving measures. Reconstruction of the boiler room and connection to engineering networks at the address: Televiziyna Street, 3n, Kryvyi Rih, Dnipropetrovsk region

Technical Solution 2

Energy saving measures. Reconstruction of the boiler room with the installation of solid fuel boilers and connection to engineering networks at the address: Televeziyna Street, 3n, Kryvyi Rih, Dnipropetrovsk region

Total costs1'212'427'977 UAH2'277'000'000 UAH
  • For preparation
  • 10'389'788 UAH2'000'000 UAH
  • For implementation
  • 539'014'114 UAH1'750'000'000 UAH
  • For operation
  • 663'024'075 UAH350'000'000 UAH
  • For closing
  • 0 UAH175'000'000 UAH
    Average annual costs26'520'963 UAH17'500'000 UAH
    Project duration, incl.30 months18 months
  • Deadline for developing a FFS
  • 18 months6 months
  • Implementation period
  • 12 months12 months
    Service life300 months240 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    What procurement strategy was chosen for the project implementation, and what justifies its feasibility in the context of the market and project objectives?
    Реалізація проєкту передбачається на підставі вигоровлення проєктно-кошторисної документації

    [Response was provided in the Investment Feasibility Study]

    What approaches are planned to be used to ensure transparency, competition, and efficiency in the procurement process?
    для забезпечення прозорості, конкуренції та ефективності в процесі закупівель буде використано електроний майданчик ProZorro,

    [Response was provided in the Investment Feasibility Study]

    What types of procurement procedures are envisaged by the project (open tender, negotiated procedure, competitive dialogue, etc.)?
    Open competitive bidding

    [Response was provided in the Investment Feasibility Study]

    Pre-market engagement
    Попереднє залучення ринку здійснювалося для оцінки доступних технологій, постачальників обладнання та підрядників для реконструкції котельні та приєднання до інженерних мереж на вул. Телевезійна, 3н, Кривий Ріг. Було використано такі джерела та інструменти: Огляд відкритих тендерів та закупівель – аналіз публічних тендерів на «Прозорро» та аналогічних проєктів для оцінки ринкових цін і пропозицій. Прямі запити до компаній – отримання технічних характеристик та умов постачання котельного обладнання і теплообмінників. Аналіз аналогічних проєктів – вивчення реалізованих проєктів модернізації котелень і теплових мереж для оцінки витрат і технологій. Результатом стало визначення оптимальних технологічних рішень, орієнтовних ринкових цін та потенційних постачальників, що дозволяє обґрунтовано планувати бюджет і технічні рішення проєкту.

    [Response was provided in the Investment Feasibility Study]

    Potential market participants
    На ринку реалізації проєкту можуть брати участь: Постачальники обладнання – виробники котлів, насосів, теплообмінників, систем автоматики та енергоменеджменту. Будівельно-монтажні організації – підрядники з будівництва та реконструкції котельні, монтажу теплових мереж та інженерних комунікацій. Інженерно-консультаційні компанії – проєктувальники котельних та тепломереж, енергетичні аудитори, фахівці з енергоефективності. Організації з охорони довкілля та санітарії – компанії, що здійснюють контроль викидів, очищення стоків, утилізацію відходів, моніторинг шуму та якості води. Державні та муніципальні структури – місцеві тепло- та енергокомпанії, санітарно-епідеміологічні та екологічні служби, що здійснюють контроль та погодження проєктних рішень.

    [Response was provided in the Investment Feasibility Study]

    Market readiness assessment
    Ринок готовий до реалізації подібного проєкту: наявність кваліфікованих виконавців, доступність технологій / ресурсів.

    [Response was provided in the Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget1'212'427'977 UAH2'277'000'000 UAH
    Capital costs1'212'427'977 UAH2'277'000'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation10'389'788 UAH2'000'000 UAH
    For implementation539'014'114 UAH1'750'000'000 UAH
    For operation663'024'075 UAH350'000'000 UAH
    For closing0 UAH175'000'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitСередня вартість проєкту на одного отримувача послуги або одиницю продукції
    Service Unit Cost15'802 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo
    Is the project self-sustaining?No

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds60'389'788 UAH0 UAH
    Expected Funds60'389'788 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic feasibility study - technical expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Partially, we have limited experience

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    None of the options are applicable
    Is there an understanding of where to find relevant experts and consultants?
    Yes, negotiations are already underway.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project management structure defined: working group, chair, project team?
    Yes

    [Response was provided in the Investment Feasibility Study]

    What categories of experts and consultants have already been involved at the project preparation stage?
    None of the options are applicable
    Are there plans to involve experts and consultants for further implementation of the project?
    No

    [Response was provided in the Investment Feasibility Study]

    Risk assessment

    Technical riskDefinedUndefined
    Financial riskDefinedUndefined
    Market riskDefinedUndefined

    Organizational events

    ResponseDefinedUndefined

    Team involvement

    How exactly are/will stakeholders be involved?
    Public hearings

    [Response was provided in the Investment Feasibility Study]

    When are/will engagement activities be taking place?
    At the project preparation stage

    [Response was provided in the Investment Feasibility Study]

    How is/will the public be informed about the importance of participation and available channels for feedback?
    Social networks

    [Response was provided in the Investment Feasibility Study]

    Local media

    [Response was provided in the Investment Feasibility Study]

    Are public hearings being held/will they be held (offline, online)?
    Yes, online

    [Response was provided in the Investment Feasibility Study]

    реєстраційна справа в Єдиному реєстрі з оцінки впливу на довкілля № 13275 (в режимі відеоконференції)
    Who will attend the public hearings?
    Representatives of public organizations

    [Response was provided in the Investment Feasibility Study]

    Community representatives

    [Response was provided in the Investment Feasibility Study]

    Public hearings have already been held
    Yes

    [Response was provided in the Investment Feasibility Study]

    загальну інформацію про результати проведених слухань: ПРОТОКОЛ громадських слухань щодо "Заходи з енергозбереження. Реконструкция котельні та приєднання до інженерних мереж за адресою: вулиця Телевезійна, 3н, м. Кривий Ріг, Дніпропетровська область" реєстраційна справа в Єдиному реєстрі з оцінки впливу на довкілля № 13275 (в режимі відеоконференції) відбулися 18.11.2025 p. o 14:00; Кількість учасників громадських слухань - 14 людей; Протокол і Висновок додано у комплект документів.
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the project require preparation assistance from Project Preparation Programs (PPF)?

    None of the options are applicable

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable
    Need for financing

    Does the project require additional funding for preparation?

    No
    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    10/02/2026SP-L-100226-ACE15C55Community SPInvestment Feasibility StudyInclude-
    17/02/2026SPP-L-170226-D7E51C3CCommunity SPPInvestment Feasibility StudyInclude-