General information
Description of the project
The project involves the construction of a new transformer substation to electrify the promising Dobryninsky residential district in Slavutych, which is intended for development by participants in the Anti-Terrorist Operation/Joint Forces Operation and their families. Currently, the development of the area is critically limited by a lack of power: the existing networks are only capable of supplying about 50 households, which makes further construction and settlement of the territory impossible.
The technical solution involves the installation of a complete transformer substation (CTS) with two power transformers, each with a capacity of 630 kVA (2x630 kVA). The implementation of the project will create the necessary power reserve, which will allow increasing the number of connected subscribers from the current 50 to 400 private houses, which will give impetus to the full development of the neighborhood and provide housing for the families of Ukraine's defenders.
The purpose of the project
Main Goal:
Developing new territories or functions
Secondary Goal:
Capacity building, Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
1200 human
Number of IDPs in the geographical area of impact of the project
1325 human
Population in the geographical area of influence of the project
18247 human
Strategic Case
Strategic feasibility of the project
Sector
Energy Sector
Subsector
Electric power industry
Stream
Energy infrastructure and energy efficiency
Strategic document
Стратегія розвитку територіальної громади
Task
5 Implementation of distributed generation
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Installation of a complete transformer substation (CTS) with two power transformers with a capacity of 630 kVA each (2x630 kVA)
Technical Solution 2
Installation of a single-transformer complete substation with a capacity of 1250 kVA (KTP 1x1250 kVA)
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]