Reconstruction of the medical building of the Municipal Non-Profit Enterprise of the Ivankiv Village Council Ivankiv "Central District Hospital" at 65 Poliska Street in the village of Ivankiv, Vyshhorod district, Kyiv region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the reconstruction of the medical building of the Municipal Non-Profit Enterprise of the Ivankiv Village Council «Central District Hospital», located at: Kyiv region, Vyshgorod district, Ivankiv town, 65 Poliska St. The goal of the project is to improve the quality of medical services, create modern conditions for patients and staff, ensure energy efficiency and safety of the building. The implementation of the project will include a complex of construction and engineering works, modernization of internal premises and life support systems, renewal of engineering networks, as well as the installation of modern medical equipment. The reconstruction will increase the functionality of the hospital, provide comfortable and safe conditions for patients and medical staff, optimize the use of energy resources and contribute to improving the accessibility of medical care for residents of the Ivankiv community.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
100 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Construction, reconstruction, overhaul of healthcare facilities in Kyiv region
Strategic document
Регіональна стратегія розвитку
Task
1.2.2 Formation of a capable network of cluster and supracluster healthcare institutions in the Kyiv region.
Project objectives
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Reconstruction of the medical building of the Municipal Non-Profit Enterprise of the Ivankiv Village Council Ivankiv "Central District Hospital" at 65 Poliska Street in the village of Ivankiv, Vyshhorod district, Kyiv region
Technical Solution 2
New construction
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]