Creation of the "Southern Dental Rehabilitation Center of the Ministry of Health of Ukraine" on the basis of the State Non-Profit Enterprise "Basin Dental Polyclinic of the Ministry of Health of Ukraine"


Sector
Healthcare
Stream
Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
State level of SP
Investment Feasibility Study
Implementation
Completion

General information

Description of the project

From August 2022 to February 2026, the number of appeals from servicemen of the Armed Forces of Ukraine exceeded 10,000 people. Over the last period, the number of appeals from servicemen has been increasing. Given the significant number of Defenders who received mine-explosive facial injuries, gunshot facial injuries and other complex injuries, the issue of creating a department of maxillofacial surgery and plastic and reconstructive surgery with subsequent rehabilitation on the basis of the State Educational Service "BSP of the Ministry of Health of Ukraine" arose.

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Creation of new jobs through project implementation, Meeting demand

Description of the purpose of the project and ways to achieve it

Providing high-quality specialized dental care: - to military personnel of the Armed Forces of Ukraine, - to war veterans, -coordination of organizational and methodological work aimed at increasing the effectiveness of treatment and rehabilitation of military personnel of the Armed Forces of Ukraine and war veterans.

Problems and solutions resulting from project implementation

As a result of the implementation of the aforementioned project, the creation of a rehabilitation center will enable military personnel and war veterans to receive high-quality specialized dental care due to mine and gunshot facial injuries and return them to a full life.

Socio-economic context

Indicator

Value

Capital expenditure per year

50 mln UAH

Number of people who will use the service

5 thous. people

Number of employees of the institution/institution/organization

250 human

Strategic Case

Strategic feasibility of the project

Sector

Healthcare

Subsector

Specialized medical care

Stream

Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities

Strategic document

Strategy for the Development of the Healthcare System until 2030

Task

Strategic goal 1 Ensuring universal access of the population to quality medical services and tools for implementing the right to health

Project objectives

Indicator
Base value
Target value
Ensuring the provision of high-quality specialized dental care to military personnel of the Armed Forces of Ukraine and war veterans
5 thous. people
10 thous. people

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Щомісячне оброблення статистичних даних звернень військовослужбовців ЗСУ до ДНП "БСП МОЗ України"
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
10 thous. people
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Alternative technical solutions

Technical Solution 1

Creation of the "Southern Dental Rehabilitation Center of the Ministry of Health of Ukraine" on the basis of the State Non-Profit Institution "Baseynova Dental Polyclinic of the Ministry of Health of Ukraine"

Technical Solution 2

Modernization of the building of the "SSS" SONYACHNYI" (ODESA CITY) Ministry of Health of Ukraine)

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)84'000'000 UAH10'000'000 UAH
For preparation4'000'000 UAH5'000'000 UAH
For implementation80'000'000 UAH5'000'000 UAH
Project operation and closure cost5'000'000 UAH2'000'000 UAH
For operation4'000'000 UAH1'000'000 UAH
For closing1'000'000 UAH1'000'000 UAH
Average annual costs25'000'000 UAH25'000'000 UAH
Project duration, incl.30 months24 months
Deadline for developing a FFS12 months12 months
Implementation period18 months12 months
Service life600 months12 months
Target indicatorsDefined Not defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Pending

[The project initiator has not taken any decision about this alternative technical approach.]

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget89'000'000 UAH12'000'000 UAH
Project cost (preparation and implementation)84'000'000 UAH10'000'000 UAH
For preparation4'000'000 UAH5'000'000 UAH
For implementation80'000'000 UAH5'000'000 UAH
Project operation and closure cost5'000'000 UAH2'000'000 UAH
For operation4'000'000 UAH1'000'000 UAH
For closing1'000'000 UAH1'000'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service Unitнадання стаціонарної стоматологічної допомоги з подільшою реабілітацією
Service Unit Cost50'000 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
No, this is the first project of its kind.

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Is there an understanding of where to find relevant experts and consultants?
Yes, negotiations are already underway.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Economic riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project require preparation assistance from Project Preparation Programs (PPF)?

None of the options are applicable
Need for financing

Does the project require additional funding for preparation?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
11/03/2026SP-N-110326-AC105B75State SPPreliminary Investment Feasibility StudyInclude--