Technical re-equipment of primary electrical connections of substation No. 133, Bucha, 9-P Instytutska
Sector
Energy Sector
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The transformer substation is existing, separately located and consists of separate premises: RU-10 kV, RU-0.4 kV, transformer premises T1 and T2. Ventilation of the transformer premises with natural air movement through louvered grilles. Facility address: Bucha, 9-P Instytutska St. The facility is in the communal property of the Bucha City Council. The transformer substation was damaged as a result of Russian armed aggression approximately on 01.03.2022 and was destroyed and requires reconstruction measures.
The purpose of the project
Main goal:
Rebuilding the damaged/destroyed
Secondary goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Improving the technical level and reliability of the community's electrical network by updating primary electrical connections and implementing modern technical solutions that will ensure stable and uninterrupted power supply. Currently, the primary electrical connections of the transformer substation have a high degree of wear, which leads to frequent failures, power losses and reduced reliability of power supply. Outdated equipment does not meet modern requirements for energy efficiency, safety and automation.
The implementation of the project will eliminate these shortcomings, bringing the technical condition of the substation to a modern level, which will ensure the continuity of electricity supply, reduce losses and improve the quality of power supply for the population and enterprises of the community.
Problems and solutions resulting from project implementation
High degree of wear and tear of transformer substation equipment. Low reliability and stability of power supply. Lack of modern automation and monitoring systems. Insufficient network capacity when load increases. Increased electricity losses and frequent emergency shutdowns.
Socio-economic context
Indicator
Value
Capacity
180 kW
Strategic Case
Strategic feasibility of the project
Sector
Energy Sector
Subsector
Electric power industry
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Strategic document
Task
A.2.5.3. Implementation of Municipal Energy Plan measures
Project objectives
Indicator
Base value
Target value
Demand for the service and its dynamics
Indicator
Year
Demand
Annual demand for services/infrastructure
1
340 MWh
Annual demand for services/infrastructure
2
360 MWh
Annual demand for services/infrastructure
3
370 MWh
Economic justification
Alternative technical solutions
Technical Solution 1
Technical re-equipment of primary electrical connections of substation No. 133, Bucha, 9-P Instytutska
Technical Solution 2
Construction of a new transformer substation
Total costs8'881'000 UAH27'500'000 UAH
Average annual costs740'000 UAH1'000'000 UAH
Project duration, incl.9 months36 months
Service life120 months240 months
Target indicatorsDefined Defined
Technical Solution Status
Active
[The technical approach was selected for further detailed analysis or implementation.]
Rejected
[The technical approach was not selected for further detailed analysis or implementation.]
Components of a technical solution
Financial justification
Total project budget
Total preliminary budget8'881'000 UAH27'500'000 UAH
Capital costs8'881'000 UAH27'500'000 UAH
Operational costs0 UAH0 UAH
Preliminary cost breakdown
Operating costs for implementation0 UAH0 UAH
For preparation350'000 UAH2'000'000 UAH
For implementation7'050'000 UAH20'000'000 UAH
For operation1'480'000 UAH500'000 UAH
For closing1'000 UAH5'000'000 UAH
Average project cost per service recipient
Service UnitРемонт трансформаторної підстанції
Service Unit Cost7'400'000 UAH
Profitability of the project
Is the project expected to generate income?
ResponseYesNo
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo
Funding Sources
Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH
Management Rationale
Risk assessment
Other riskDefinedUndefined