Technical re-equipment of primary electrical connections of substation No. 133, Bucha, 9-P Instytutska


Sector
Energy Sector
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Maturity level
88
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The transformer substation is existing, separately located and consists of separate premises: RU-10 kV, RU-0.4 kV, transformer premises T1 and T2. Ventilation of the transformer premises with natural air movement through louvered grilles. Facility address: Bucha, 9-P Instytutska St. The facility is in the communal property of the Bucha City Council. The transformer substation was damaged as a result of Russian armed aggression approximately on 01.03.2022 and was destroyed and requires reconstruction measures. 

The purpose of the project

Main goal:

Rebuilding the damaged/destroyed

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

Improving the technical level and reliability of the community's electrical network by updating primary electrical connections and implementing modern technical solutions that will ensure stable and uninterrupted power supply. Currently, the primary electrical connections of the transformer substation have a high degree of wear, which leads to frequent failures, power losses and reduced reliability of power supply. Outdated equipment does not meet modern requirements for energy efficiency, safety and automation. The implementation of the project will eliminate these shortcomings, bringing the technical condition of the substation to a modern level, which will ensure the continuity of electricity supply, reduce losses and improve the quality of power supply for the population and enterprises of the community.

Problems and solutions resulting from project implementation

High degree of wear and tear of transformer substation equipment. Low reliability and stability of power supply. Lack of modern automation and monitoring systems. Insufficient network capacity when load increases. Increased electricity losses and frequent emergency shutdowns.

Socio-economic context

Indicator

Value

Capacity

180 kW

Strategic Case

Strategic feasibility of the project

Sector

Energy Sector

Subsector

Electric power industry

Stream

Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)

Strategic document

Стратегія розвитку територіальної громади

Task

A.2.5.3. Implementation of Municipal Energy Plan measures

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Оцінка попиту здійснювалась на основі комплексного аналізу фактичного споживання електроенергії за останні роки, прогнозу розвитку Бучанської громади та демографічних тенденцій, включно зі зростанням кількості внутрішньо переміщених осіб. Методологія поєднувала статистичний аналіз, нормативні розрахунки питомого навантаження та сценарне прогнозування з урахуванням активного житлового будівництва, розвитку соціальної, комунальної й промислової інфраструктури. Додатковим чинником стала необхідність підвищення стійкості енергомереж до постійних обстрілів енергосистеми, що призводять до збоїв і пошкоджень обладнання. Результати аналізу показали зростання попиту на електроенергію та критичну потребу у модернізації підстанції для забезпечення стабільного, безпечного й безперебійного електропостачання в умовах воєнних ризиків і динамічного розвитку громади.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
340 MWh
Annual demand for services/infrastructure
2
360 MWh
Annual demand for services/infrastructure
3
370 MWh
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Envisaged training or advanced training for women in the private sector
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
economic analysis.docx
09.12.2025
11:06:42 UTC

Alternative technical solutions

Technical Solution 1

Technical re-equipment of primary electrical connections of substation No. 133, Bucha, 9-P Instytutska

Technical Solution 2

Construction of a new transformer substation

Total costs8'881'000 UAH27'500'000 UAH
  • For preparation
  • 350'000 UAH2'000'000 UAH
  • For implementation
  • 7'050'000 UAH20'000'000 UAH
  • For operation
  • 1'480'000 UAH500'000 UAH
  • For closing
  • 1'000 UAH5'000'000 UAH
    Average annual costs740'000 UAH1'000'000 UAH
    Project duration, incl.9 months36 months
  • Deadline for developing a FFS
  • 3 months12 months
  • Implementation period
  • 6 months24 months
    Service life120 months240 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget8'881'000 UAH27'500'000 UAH
    Capital costs8'881'000 UAH27'500'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation350'000 UAH2'000'000 UAH
    For implementation7'050'000 UAH20'000'000 UAH
    For operation1'480'000 UAH500'000 UAH
    For closing1'000 UAH5'000'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitРемонт трансформаторної підстанції
    Service Unit Cost7'400'000 UAH

    Profitability of the project

    Is the project expected to generate income?YesNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    Yes, the project is suitable for PPP

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic feasibility study - technical expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Yes, successfully implemented 1 or more similar projects

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    Management rationale - public consultation

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management rationale - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management rationale - working with international financial organizations (IFOs)

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is there an understanding of where to find relevant experts and consultants?
    Yes, negotiations are already underway.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Other riskDefinedUndefined

    Team involvement

    How exactly are/will stakeholders be involved?
    Focus group

    [Response was provided in the Investment Feasibility Study]

    Meetings with local authorities

    [Response was provided in the Investment Feasibility Study]

    Public consultations

    [Response was provided in the Investment Feasibility Study]

    Public hearings

    [Response was provided in the Investment Feasibility Study]

    When are/will engagement activities be taking place?
    At the project preparation stage

    [Response was provided in the Investment Feasibility Study]

    How is/will the public be informed about the importance of participation and available channels for feedback?
    Social networks

    [Response was provided in the Investment Feasibility Study]

    Local media

    [Response was provided in the Investment Feasibility Study]

    Are public hearings being held/will they be held (offline, online)?
    Yes, online

    [Response was provided in the Investment Feasibility Study]

    Проводилися в Міській раді
    Who will attend the public hearings?
    Representatives of public organizations

    [Response was provided in the Investment Feasibility Study]

    Experts

    [Response was provided in the Investment Feasibility Study]

    Community representatives

    [Response was provided in the Investment Feasibility Study]

    Government officials

    [Response was provided in the Investment Feasibility Study]

    Public hearings have already been held
    No

    [Response was provided in the Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
    09/12/2025SP-L-091225-73FBA225Community SPInvestment Feasibility StudyInclude--
    22/12/2025SPP-L-221225-09897B41Community SPPInvestment Feasibility StudyIncludeDecision of the Local Investment Council Minutes No. 7 dated 12/22/202588