Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

The project involves major repairs and renovation of the basement of the preschool educational institution "Malyatko" of the Novorozdil City Council at the address: Tarasa Shevchenko Avenue, 32v, Novy Rozdil, Lviv region. The purpose of the project is to create safe conditions for children and employees during emergencies by bringing the basement into compliance with the requirements of a civil defense protective structure (shelter). The project plans to: perform repair and construction work (waterproofing, repair of the floor, walls, ceiling, arrangement of entrances and emergency exits); install ventilation, lighting, water supply and drainage systems; provide the necessary engineering and sanitary equipment. Expected results: creation of a safe, functional and usable shelter for children and employees of the institution; increasing the level of community preparedness for emergencies; improving the conditions of stay in the educational institution.

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Increasing compliance with modern standards, Improving the quality of services

Description of the purpose of the project and ways to achieve it

The goal of the project is to create a safe, comfortable and functional shelter in the basement of the preschool educational institution "Malyatko" of the Novorozdil City Council, which will ensure the protection of children and employees during emergencies of a military or technogenic nature. The project is aimed at increasing the level of safety of the educational environment, compliance of the facility with the requirements of legislation in the field of civil protection and creation of appropriate conditions for a continuous educational process even under threat.

Problems and solutions resulting from project implementation

Key issues to be addressed by the project Lack of safe conditions for sheltering children and staff during emergencies. The basement of the preschool educational institution "Malyatko" currently does not meet the requirements for protective structures of civil defense. There is no proper waterproofing, ventilation, emergency lighting system, sanitary and household conditions and an evacuation exit. This makes it impossible for children to stay safely during an air raid or other threats. Physical and moral wear and tear of the premises. The basement of the institution is in unsatisfactory technical condition: there are traces of moisture, damage to the plaster, insufficient lighting and a lack of fire prevention measures. Such an environment poses a danger to the health of children and staff. The facility does not comply with the requirements of the legislation in the field of civil defense. According to the requirements of the Civil Defense Code of Ukraine and the relevant State Standards, all educational institutions must be provided with shelters or the simplest storage facilities. The absence of such a facility creates a violation of safety standards and a threat to the lives of participants in the educational process. Expected positive changes as a result of the project implementation creation of a full-fledged civil defense structure for children and employees of the institution; ensuring a safe environment and psychological comfort for participants in the educational process; increasing the level of community preparedness for emergencies; restoration and improvement of the technical condition of the institution's premises; ensuring the uninterrupted operation of the kindergarten even under martial law.

Socio-economic context

Indicator

Value

Number of IDP users

7 human

Number of people who will use the service

235 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

Preschool education

Stream

Arrangement of civil defense structures (shelters) in preschool educational institutions

Strategic document

Стратегія розвитку територіальної громади

Task

3.1.3. Improve the material and technical support of educational institutions

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз чисельності цільової аудиторії (діти та працівники) та розрахунок необхідної місткості укриття
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
235 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis analysis ZDO Malyatko.pdf
08.11.2025
20:22:21 UTC

Alternative technical solutions

Technical Solution 1

Major repairs and arrangement of the basement of the civil defense protective structure (shelter) in the "Malyatko" ZDO of the Novorozdil City Council at the address: Tarasa Shevchenko Avenue, 32 v, Novyy Rozdil, Lviv region

Technical Solution 2

Construction of a civil defense structure (shelter) in the "Malyatko" residential area of the Novorozdil City Council

Total costs7'710'001 UAH46'120'000 UAH
  • For preparation
  • 350'000 UAH1'000'000 UAH
  • For implementation
  • 7'350'000 UAH45'000'000 UAH
  • For operation
  • 10'000 UAH100'000 UAH
  • For closing
  • 1 UAH20'000 UAH
    Average annual costs40'000 UAH150'000 UAH
    Project duration, incl.18 months45 months
  • Deadline for developing a FFS
  • 6 months9 months
  • Implementation period
  • 12 months36 months
    Service life360 months600 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget7'710'001 UAH46'120'000 UAH
    Capital costs7'710'001 UAH46'120'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation350'000 UAH1'000'000 UAH
    For implementation7'350'000 UAH45'000'000 UAH
    For operation10'000 UAH100'000 UAH
    For closing1 UAH20'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitСередня вартість проєкту на одного отримувача послуг
    Service Unit Cost32'766 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Partially, we have limited experience

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    Economic feasibility study - technical expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is there an understanding of where to find relevant experts and consultants?
    Partially, we are considering options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Financial riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    08/11/2025SP-L-081125-125CA88ECommunity SPInvestment Feasibility StudyIncludeStrategic fit confirmed
    20/01/2026SP-N-200126-0D4AD84EState SPInvestment Feasibility StudyInclude-
    12/11/2025SPP-L-121125-2FACAE43Community SPPInvestment Feasibility StudyInclude-