General information
Description of the project
Project involves design, development and installation of 4 microgrids in the city of Ternopil. These will include several generation assets: existing Gas Engine/Trubine CHP, PV plant, Battery, Substation automation and protection and Energy Management System. When installed the microgrids will be able to provide electrical power and some heating for the part of the city. More importantly they will be able to able to provide this power at times when the grid is unavailable, because they can work in islanded (off-grid) mode. Additionally, critical comsumers in that part of the city, such as ambulance, police and other critical infrastructure would be supplied. With the Energy Management System and Substation automation a lot of the operational work will be automated and more secure.
The purpose of the project
Main Goal:
Introducing innovations and energy-efficient solutions
Secondary Goal:
Contribution to climate or environmental goals, Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the condition of infrastructure, Improving the quality of services, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capital expenditure per year
735 mln UAH
Number of people who will use the service
200000 human
Population in the geographical area of influence of the project
200000 human
Strategic Case
Strategic feasibility of the project
Sector
Energy Sector
Subsector
Electric power industry
Stream
Modernization and development of distribution electricity networks with the introduction of "smart grid" technologies
Strategic document
Концепція впровадження «розумних мереж» в Україні до 2035 року
Task
Increasing the reliability of energy supply to consumers, implementing automated distribution network management systems, reducing electricity losses, frequency and duration of consumer outages
Project objectives
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Ternopil microgrid
Technical Solution 2
Do not carry out reconstruction activities
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]