New construction of the 330 kV Kvartsit - Pershotravneva transmission line with the reconstruction of the 330 kV Kvartsit substation and the 330 kV Pershotravneva substation, Kirovohrad and Dnipropetrovsk regions


Sector
Energy Sector
Stream
Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

Due to the full-scale Russian military aggression and the damage caused by it to the elements of the Ukrainian Unified Power System, the operating modes of the "Southern Ukrainian NPP - Dnipro" section in the current scheme of the electric grid and in the conditions of the available sources of generating equipment are currently extremely difficult and require the use of operational measures related to the redispatching of thermal and hydroelectric power plants in the daily dispatch schedule to maintain them. The active military actions of the Russian aggressor and the occupation of generating capacities lead to the fact that the operating modes of the power system in terms of ensuring the maximum permissible power flow in the specified controlled section may become even more complicated and will require the use of forced consumption restrictions in the eastern part of the Ukrainian Unified Power System. Currently, the operating modes of the electric grid and the existing generation composition of the Ukrainian Unified Power System have determined the maximum load of the "Southern Ukrainian NPP - Dnipro" section. Dnipro, while the highest load is achieved by the 330 kV Kvartsyt – Rudna overhead line. At the same time, due to the non-completion of the power grid construction on the part of the 330 kV Kvartsyt – substation, the 330 kV South Ukrainian NPP – Kvartsyt No. 1 overhead line was not connected according to the design scheme in 1992. Currently, the overhead line is connected to a protective voltage of 150 kV on the part of the 330 kV Kvartsyt – substation, and the 330 kV South Ukrainian NPP – Kvartsyt No. 2 overhead line operates at maximum permissible power values in emergency and repair modes.

The purpose of the project

Main goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

Strengthening the connection of the South Ukrainian NPP to the 330 kV networks in the event of an unforeseen situation with the generation of the Zaporizhzhia NPP due to the military aggression of the Russian Federation against Ukraine, reducing the technological costs of electricity for its transmission, increasing the reliability of electricity supply to consumers in the Kirovohrad and Kryvyi Rih energy districts

Problems and solutions resulting from project implementation

The implementation of the Project will increase the reliability of electricity supply to consumers in the northern region of Ukraine

Socio-economic context

Indicator

Value

Other functional

1 %

Strategic Case

Strategic feasibility of the project

Sector

Energy Sector

Subsector

Electric power industry

Stream

Creation of new, expansion, reconstruction, technical re-equipment of existing energy infrastructure facilities (high-voltage power transmission lines, substations, high-voltage equipment, etc.)

Strategic document

Energy Strategy of Ukraine until 2050

Task

Ensuring a stable, balanced model of operation of the Unified Power System of Ukraine; restoration, development and transformation of the power system, its sustainable operation;; increasing the efficiency of substations

Project objectives

Indicator
Base value
Target value
Increasing reliability of electricity supply
1 %
2 %
Economic justification

Alternative technical solutions

Technical Solution 1

Construction of the 330 kV Kvartsyt – Pershotravneva overhead line. Reconstruction of the 330 kV substations of the Kvartsyt and Pershotravneva substations with the equipment of the corresponding connections for the possibility of connecting the 330 kV overhead line. Construction of a linear connection on the 330 kV substation of the Kvartsyt substation for connecting the 330 kV overhead line of the South Ukrainian NPP – Kvartsyt No. 1.

Technical Solution 2

Not provided

Total costs1'919'700'002 UAH4 UAH
  • For preparation
  • 53'460'000 UAH1 UAH
  • For implementation
  • 1'866'240'000 UAH1 UAH
  • For operation
  • 1 UAH1 UAH
  • For closing
  • 1 UAH1 UAH
    Average annual costs1 UAH1 UAH
    Project duration, incl.42 months2 months
  • Deadline for developing a FFS
  • 6 months1 month
  • Implementation period
  • 36 months1 month
    Service life600 months1 month
    Target indicatorsDefined Defined
    Technical Solution Status
    Active
    Rejected
    Components of a technical solution
    To components
    0
    To components
    0

    Financial justification

    Total project budget

    Total preliminary budget1'919'700'002 UAH4 UAH
    Capital costs1'919'700'002 UAH4 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation53'460'000 UAH1 UAH
    For implementation1'866'240'000 UAH1 UAH
    For operation1 UAH1 UAH
    For closing1 UAH1 UAH

    Average project cost per service recipient

    Service UnitРозрахунки відсутні
    Service Unit Cost1 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH
    Management Rationale

    Risk assessment

    Other riskDefinedUndefined

    Organizational events

    ResponseDefinedUndefined
    Results of the feasibility analysis
    Economic Analysis
    Social benefits and costs
    Calculations were not performed
    Environmental benefits and costs
    Calculations were not performed
    Indirect benefits and costs
    Calculations were not performed