New construction of a block-modular boiler plant BMK-200, as a component of real estate on the territory of the Municipal Preschool Education Institution No. 10 "Lastivka", at the address: Voznesensk, Koroleva St., 1, Mykolaiv region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
It is planned to build a new block-modular boiler plant BMK-200 as a component of real estate on the territory of the Municipal Preschool Education Institution No. 10 "Lastivka", at the address: Voznesensk, Koroleva St., 1, Mykolaiv region. The new construction is planned in one stage, without the allocation of start-up complexes.
The purpose of the project
Main Goal:
Introducing innovations and energy-efficient solutions
Secondary Goal:
Increasing compliance with modern standards, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Operating expenses per year
156090 UAH
Capital expenditure per year
5781997 UAH
Number of employees of the institution/institution/organization
28 human
Number of IDP users
7 human
Capacity
125 human
Number of people who will use the service
125 human
Population in the geographical area of influence of the project
37400 human
Number of IDPs in the geographical area of impact of the project
2900 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
District Heating
Stream
Restoration, modernization and development of centralized and decentralized heating systems
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.2. Implementation of energy saving measures
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New construction of a block-modular boiler plant BMK-200, as a component of real estate on the territory of the Municipal Preschool Education Institution No. 10 "Lastivka", at the address: Voznesensk, Koroleva St., 1, Mykolaiv region
Technical Solution 2
New modular boiler room
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]