"Restoration of the hydrological regime by clearing the Vovcha River bed in the area of the city beach on the territory of the May 1st Park in Pavlohrad. Major repairs"


Sector
Environment
Stream
Modern ecological cultural, sports and recreational facilities
Maturity level
69
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Investment Feasibility Study
Implementation
Completion

General information

Description of the project

The project envisages the restoration and optimization of the hydrological regime of the Vovcha River within the city of Pavlohrad in a critical section of 630 meters in length to increase the capacity of the riverbed, improve water quality, and minimize the risks of flooding of nearby areas.

The purpose of the project

Main Goal:

Contribution to climate or environmental goals

Secondary Goal:

Improving the equality of wealth distribution

Description of the purpose of the project and ways to achieve it

The main goal of the project: Restoration and optimization of the hydrological regime of the Vovcha River within the city of Pavlohrad in a critical section of 630 meters in length to increase the capacity of the riverbed, improve water quality and minimize the risks of flooding of nearby areas. The method of achievement is through clearing

Problems and solutions resulting from project implementation

The main problem is the violation of the natural hydrological and hydrobiological regime of the Vovcha River within the city of Pavlohrad, namely: critical siltation of the riverbed, overgrowth and clutter, and reduced throughput.

Socio-economic context

Indicator

Value

Other functional

630 m

Strategic Case

Strategic feasibility of the project

Sector

Environment

Subsector

Water protection, water management development, flood risk mitigation, centralized water supply, management, use and restoration of surface water resources

Stream

Modern ecological cultural, sports and recreational facilities

Strategic document

Стратегія розвитку територіальної громади

Task

A.3.3. Restoration of the hydrological regime by clearing the Vovcha River bed in the area of the city beach in the territory of the 1 Travnya Park in Pavlohrad

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Alternative technical solutions

Technical Solution 1

"Restoration of the hydrological regime by clearing the Vovcha River bed in the area of the city beach on the territory of the May 1st Park in Pavlohrad. Major repairs"

Technical Solution 2

introduction of aquatic organisms (launching fish to clean the river bottom)

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)50'350'698 UAH1'000'000 UAH
For preparation350'697 UAH0 UAH
For implementation50'000'001 UAH1'000'000 UAH
Project operation and closure cost0 UAH0 UAH
Average annual costs0 UAH1'000'000 UAH
Project duration, incl.18 months3 months
Deadline for developing a FFS6 months1 month
Implementation period12 months2 months
Service life60 months24 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget50'350'698 UAH1'000'000 UAH
Project cost (preparation and implementation)50'350'698 UAH1'000'000 UAH
For preparation350'697 UAH0 UAH
For implementation50'000'001 UAH1'000'000 UAH
Project operation and closure cost0 UAH0 UAH
For operation0 UAH0 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service Unit1 м розчистки
Service Unit Cost76'923 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project require preparation assistance from Project Preparation Programs (PPF)?

None of the options are applicable
Need for financing

Does the project require additional funding for preparation?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
20/10/2025SP-L-201025-FF2DF6FACommunity SPPreliminary Investment Feasibility StudyInclude--
22/10/2025SPP-L-221025-D58F04D9Community SPPPreliminary Investment Feasibility StudyInclude-69