"Reconstruction of the water supply pipeline on Ozerna Street in Pavlohrad". Correction


Sector
Municipal infrastructure and services
Stream
Development/renovation of urban infrastructure
Maturity level
68
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project provides for: reconstruction of the water supply system along Ozerna Street from Central Street to Oleny Bdzhilka Street, from Central Street to Borys Zahava Street, from Borys Zahava Street to Oleny Bdzhilka Street. The pipeline is laid parallel to the existing route with the reconnection of existing subscribers. Expected result: providing consumers with high-quality drinking water by performing underground laying of a water supply pipeline 1925.56 m long using polyethylene pipelines with high hydraulic characteristics

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

Providing consumers with high-quality drinking water by performing underground water supply pipeline laying works using polyethylene pipelines with high hydraulic characteristics

Problems and solutions resulting from project implementation

The pipeline is worn out and in a state of emergency. Goal: to ensure a sustainable, uninterrupted water supply and high-quality drinking water for city residents

Socio-economic context

Indicator

Value

Number of IDP users

400 thous. people

Number of people who will use the service

4 thous. people

Other functional

1 units

Other functional

50 units

Other functional

1925.56 m

Other functional

12 units

Other functional

19 units

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Development/renovation of urban infrastructure

Strategic document

Стратегія розвитку територіальної громади

Task

D.1.1.; D.1.5.; D.1.8.; D.1.10. Alternative sources of drinking water supply; Construction, reconstruction and overhaul of the city's water supply and sewage system; Reconstruction of the Pavlohrad water intake, stage I; Construction of treatment facilities

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Ozernaya.PDF
17.10.2025
15:50:41 UTC

Alternative technical solutions

Technical Solution 1

"Reconstruction of the water supply pipeline on Ozerna Street in Pavlohrad". Correction

Technical Solution 2

Alternative sources of drinking water supply

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)18'401'323 UAH1'000'000 UAH
For preparation93'624 UAH100'000 UAH
For implementation18'307'699 UAH900'000 UAH
Project operation and closure cost0 UAH10'500 UAH
For operation0 UAH10'000 UAH
For closing0 UAH500 UAH
Average annual costs5'000 UAH0 UAH
Project duration, incl.4 months7 months
Deadline for developing a FFS2 months2 months
Implementation period2 months5 months
Service life10 months120 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget18'401'323 UAH1'010'500 UAH
Project cost (preparation and implementation)18'401'323 UAH1'000'000 UAH
For preparation93'624 UAH100'000 UAH
For implementation18'307'699 UAH900'000 UAH
Project operation and closure cost0 UAH10'500 UAH
For operation0 UAH10'000 UAH
For closing0 UAH500 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unit2500
Service Unit Cost2'500 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds13'088'504 UAH0 UAH
Expected Funds13'088'504 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
20/10/2025SP-L-201025-FE3309DCCommunity SPInvestment Feasibility StudyInclude--
22/10/2025SPP-L-221025-3C21E27ECommunity SPPInvestment Feasibility StudyInclude-68