Major repairs to the landscaping project, namely part of the green zone on 2-a Naberezhna Street with the construction of a slip road in Mykolaiv


Sector
Municipal infrastructure and services
Stream
Maintaining the green zone of the settlement at the proper level and improving its environmental conditions
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves the overhaul of part of the green zone located along 2-ha Naberezhna Street in the city of Mykolaiv, with a comprehensive renovation of the territory and the arrangement of a slipway (a ramp for launching and lifting small vessels onto the water).

The purpose of the project

Main Goal:

Improving the quality of services

Secondary Goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The project includes cleaning, planning, and strengthening the coastal area, reconstructing pedestrian paths, updating green spaces, installing landscaping elements (benches, trash cans, lighting), and constructing a modern and safe slipway, taking into account the technical requirements for the operation of water infrastructure.

Problems and solutions resulting from project implementation

Arrangement of pedestrian paths and safe slipways

Socio-economic context

Indicator

Value

Number of people who will use the service

300000 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Urban planning and landscaping

Stream

Maintaining the green zone of the settlement at the proper level and improving its environmental conditions

Strategic document

Стратегія розвитку територіальної громади

Task

1.3.4 Development of modern public spaces

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Slip 2-a Naberezhna.docx
08.04.2026
08:11:15 UTC
2 Embankment.docx
08.04.2026
08:11:15 UTC

Alternative technical solutions

Technical Solution 1

Major repairs to the landscaping project, namely part of the green zone on 2-a Naberezhna Street with the construction of a slip road in Mykolaiv

Technical Solution 2

Current repairs to the landscaping project, namely part of the green zone on 2-a Naberezhna Street without the construction of a slip road in Mykolaiv

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)6'892'705 UAH1'000'000 UAH
For preparation396'585 UAH0 UAH
For implementation6'496'120 UAH1'000'000 UAH
Project operation and closure cost170'801 UAH0 UAH
For operation170'800 UAH0 UAH
For closing1 UAH0 UAH
Average annual costs7'063'505 UAH0 UAH
Project duration, incl.12 months4 months
Deadline for developing a FFS6 months1 month
Implementation period6 months3 months
Service life360 months120 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget7'063'506 UAH1'000'000 UAH
Project cost (preparation and implementation)6'892'705 UAH1'000'000 UAH
For preparation396'585 UAH0 UAH
For implementation6'496'120 UAH1'000'000 UAH
Project operation and closure cost170'801 UAH0 UAH
For operation170'800 UAH0 UAH
For closing1 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitВартість на одного користувача
Service Unit Cost25 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds6'892'705 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
08/04/2026SP-L-080426-D6D74BF2Community SPInvestment Feasibility StudyInclude--
17/04/2026SPP-L-170426-93800C8CCommunity SPPInvestment Feasibility StudyInclude--