Major repairs of the Dining Room and Catering Unit of the "Myrhorod Lyceum No. 1 named after Panas Myrny of the Myrhorod City Council, Poltava Region" at the address: 173/2 Gogolya St. in the city of Myrhorod, Poltava Region


Sector
Education and science
Stream
Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

Modernization of the Catering Unit

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

Modernization of the interior and equipment

Problems and solutions resulting from project implementation

Overhaul

Socio-economic context

Indicator

Value

Number of people who will use the service

450 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)

Strategic document

Стратегія розвитку територіальної громади

Task

A.3.2.2 Creating a modern safe educational environment in educational institutions of the territorial community

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Quality nutrition.docx
06.03.2026
09:14:08 UTC

Alternative technical solutions

Technical Solution 1

Major renovation of the Dining Room and Catering Unit of the "Myrhorod Lyceum No. 1 named after Panas Myrny of the Myrhorod City Council, Poltava Region" at the address: 173/2 Gogolya St. in the city of Myrhorod, Poltava Region

Technical Solution 2

Gym renovation

Total costs15'900'000 UAH25'900'000 UAH
  • For preparation
  • 200'000 UAH200'000 UAH
  • For implementation
  • 15'000'000 UAH25'000'000 UAH
  • For operation
  • 500'000 UAH500'000 UAH
  • For closing
  • 200'000 UAH200'000 UAH
    Average annual costs500'000 UAH500'000 UAH
    Project duration, incl.36 months48 months
  • Deadline for developing a FFS
  • 12 months12 months
  • Implementation period
  • 24 months36 months
    Service life120 months120 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget15'900'000 UAH25'900'000 UAH
    Capital costs15'900'000 UAH25'900'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation200'000 UAH200'000 UAH
    For implementation15'000'000 UAH25'000'000 UAH
    For operation500'000 UAH500'000 UAH
    For closing200'000 UAH200'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitУчнів
    Service Unit Cost55'000 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    None of the options are applicable
    Does the team have experience implementing similar projects?
    No, this is the first project of its kind.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    None of the options are applicable
    Is there an understanding of where to find relevant experts and consultants?
    No, I need help.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Other riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
    06/03/2026SP-L-060326-532DB2D1Community SPInvestment Feasibility StudyIncludeRecommended to include in a sectoral portfolio-
    11/03/2026SPP-L-110326-2F035671Community SPPInvestment Feasibility StudyNot approvedReturned for correct data entry.-