General information
Description of the project
The lack of comfortable and modern conditions for receiving patients leads to low service efficiency, restrictions on preventive and diagnostic measures, and reduced accessibility of medical care for village residents. Reconstruction of part of the premises for an outpatient clinic will create a modern medical space, provide comfortable and safe conditions for patients and staff, and improve the quality and accessibility of outpatient care in the village of Dibrivka, Myrhorod district, Poltava region.
The purpose of the project
Main goal:
Improving the condition of infrastructure
Secondary goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
750 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring access to quality medical care by developing and modernizing medical infrastructure facilities
Strategic document
Стратегія розвитку територіальної громади
Task
A.5.2, A.5.2.2, A.5.2.3 B.3.2 Updating the material and technical base of healthcare institutions Comprehensive thermal modernization of municipally owned buildings Reconstruction of the polyclinic building at: 149-A Gogolya St. in Myrhorod, Poltava region Reconstruction of the KNP "Myrhorod Intensive Care Hospital" at 172 Gogolya St. in Myrhorod, Poltava region
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of part of a non-residential building for the outpatient clinic of the Myrhorod City Council of the Central Primary Health Care Center at the address: Konezavodska St., 4 in the village of Dibrivka, Poltava region
Technical Solution 2
New construction of the AZPSM on Konezavodska Street, 4 in the village of Dibrivka, Myrhorod district, Poltava region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]