Description of the project
An apartment building that suffered significant damage as a result of military operations and is subject to major repairs is located on ul. Krychevsky, 42 and is located in the Kyiv administrative district of Kharkiv.
As a result of the impact of the means of destruction, the house was damaged:
- brick wall of the 4th floor of the 2nd entrance;
- external decoration of the 2nd, 3rd entrances;
- ceiling of the 4th floor of the 2nd, 3rd entrances;
- burning of the roof of the 2nd, 3rd entrances - internal decoration of the entrances, numerous cracks in the stairwells.
In the house, in general, partial destruction of the glazing of window openings and window frames was found, the facade of the residential building was partially damaged as a result of the fire.
Working the overhaul project provides for emergency and restoration work, namely:
- dismantling of all damaged structures);
- restoration of external and internal brick walls by masonry, installation of new partitions instead of destroyed ones made of aerated concrete blocks with reinforcement;
- restoration of the damaged reinforced concrete floor slab of the 4th floor with the installation of steel beams with the subsequent execution of a section of monolithic reinforced concrete floor;
- installation of a new wooden rafter system of the roof with wood treatment with antiseptic agents and fire-resistant bioprotection;
- restoration of ventilation ducts on the attic floor by brick masonry;
- installation of roofs on the restoration areas with bitumen tiles with insulation of the attic floor;- restoration of the external drainage system of the house, snow retention system and roof fencing, installation of lightning protection;
- insulation of the basement ceiling with mineral wool;- installation of stairs on the mezzanine of the 3rd and 4th floors;
- replacement of damaged window openings (installation of window sills and window drains, repair and installation of external window slopes);
- replacement of damaged glazing of attic windows with energy-saving metal-plastic glazing with double-chamber double-glazed windows and gluing of colored film on the outside. Replacement of damaged external and internal doorways of public use and apartments with shockproof and fire-resistant metal ones;
- repair and restoration of entrance groups (including canopies above entrances to entrances and basements);
- insulation of the facade with mineral wool boards with decorative trim;
- restoration of interior trim in public areas;
- restoration of damaged internal engineering networks (cold and hot water supply, sewage, drainage, heating, ventilation).
The detailed design provides for measures for reliability and safety, protection of building structures from corrosion, lightning protection and grounding.
The purpose of the project
Main Goal:
Rebuilding the damaged/destroyed
Secondary Goal:
Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Improving the quality of services, Reducing territorial or social gaps
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
180 human
Other functional
2214.2 m2
Other functional
32548 m3
Other functional
8474.7 m2
Number of IDPs in the geographical area of impact of the project
212 thous. people
Population in the geographical area of influence of the project
1.3 mln people
Strategic Case
Strategic feasibility of the project
Sector
Housing
Subsector
Housing Reconstruction
Stream
Restoration of apartment buildings damaged as a result of the armed aggression of the Russian Federation
Strategic document
State Strategy for Regional Development for 2021–2027
Task
Operational objective 1. Ensuring integrated development of territories taking into account the interests of future generations. Point 2 Implementation of priority measures for life safety, restoration and stimulation of economic activity in territorial communities classified as recovery areas.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Emergency and restoration works (overhaul) of the multi-apartment residential building of the “Vienna House” condominium association at 42 Krychevsky Street in Kharkiv
Technical Solution 2
Emergency and restoration works (overhaul) of the multi-apartment residential building of the “Vienna House” condominium at 42 Krychevsky St. in Kharkiv with the integration of renewable energy sources
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]