Kharkivska

community since 2020


About the community
Community SPP
Community SP
Community MTP
Project archive
All sectors
All streams
221
Projects
Projects by sectors
221
Projects
Projects by goal
221
Projects
Projects by status
1'977'040,97 mln
Cost
Estimated project costs by sectors
Project code
Keyword
Budget
Status
Initiation date
Budget
Status
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (4x0.6MW; Location 11.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project involves the installation of 4 new modular gas cogeneration units with a total production capacity of 2.4 MW.
Budget216'844'081 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (1x1.5MW; Location 10.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project involves the installation of a new modular gas-fired cogeneration plant with a production capacity of 1.5 MW.
Budget136'308'801 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (2x1.56MW; Location 9.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project envisages the installation of 2 new modular gas cogeneration units with a total production capacity of 3.12 MW.
Budget276'192'311 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (2x1.56MW; Location 8.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project envisages the installation of 2 new modular gas cogeneration units with a total production capacity of 3.12 MW.
Budget275'142'311 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (2x2MW; Location 7.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project involves the installation of 2 new modular gas cogeneration units with a total production capacity of 4 MW.
Budget351'140'141 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (2x1.56MW; Location 6.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project envisages the installation of 2 new modular gas cogeneration units with a total production capacity of 3.12 MW.
Budget273'092'311 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (3x2.3MW; Location 5.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project involves the installation of 3 new modular gas cogeneration units with a total production capacity of 6.9 MW.
Budget604'270'481 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (2x1.56MW; Location 4.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kharkivska community
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project envisages the installation of 2 new modular gas cogeneration units with a total production capacity of 3.12 MW.
Budget274'042'311 UAH
Implementation period19 months
Local level of SPP
Local level of SP
Date12. 2025
SectorEnergy Sector
SubsectorThermal power industry
StatusInvestment Feasibility Study

New construction (placement) of modular gas cogeneration plants in Kharkiv (6x2.3MW; Location 3.1)

Project goal
Creation of new facilities and services. Capacity building, Increasing compliance with modern standards, Improving the condition of infrastructure, Introducing innovations and energy-efficient solutions, Поява нових виробничих потужностей, Improving the quality of services
Geography
Kochetok town
Initiator
UTILITY ENTERPRISE "KHARKIV HEAT NETWORKS"
New construction (placement) of modular gas cogeneration plants in Kharkiv
Refusal to implement the project "New construction (placement) of modular gas cogeneration plants in Kharkiv"
The project involves the installation of 6 new modular gas cogeneration units with a total production capacity of 13.8 MW.
Budget1'202'240'971 UAH
Implementation period19 months
State level of SP
Local level of SPP
Local level of SP
Date12. 2025
SectorEducation and science
SubsectorSchool education
StatusInvestment Feasibility Study

New construction of a civil defense protective structure (radiation shelter) on the territory of the municipal institution "Kharkiv Lyceum No. 162 of the Kharkiv City Council" at the address: 61064, Kharkiv, Lvivska St., 13

Project goal
Creation of new facilities and services.
Geography
Kharkivska community
Initiator
EDUCATION DEPARTMENT OF THE NOVOBAVARSKY DISTRICT ADMINISTRATION OF KHARKIV CITY COUNCIL
New construction of a protective structure of civil defense (anti-radiation shelter)
Overhaul of the shelter
"New construction of a civil defense protective structure (radiation shelter)" — is a new, separate or built-in structure that provides protection for people from the consequences of emergencies, in particular from ionizing radiation. Such a structure is intended for sheltering the population, staff and students of educational institutions, and in peacetime can be used for economic needs.
Budget195'893'648 UAH
Implementation period15 months

In focus

All news