Overhaul of water heating boiler No. 2 PTVM-50 of the boiler house at 95 I. Bohuna St. in the city of Kherson


Sector
Municipal infrastructure and services
Stream
Modernization of the heating system (overhaul, reconstruction and arrangement of heating stations)
Maturity level
91
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project provides for the overhaul of water heating boiler No. 2 PTVM-50 of the boiler house at 95 I. Bohuna St. in the city of Kherson, which will ensure stable operation of the boiler equipment.

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Improving the quality of services

Description of the purpose of the project and ways to achieve it

Problems and solutions resulting from project implementation

The PTVM-150 boiler unit is installed in the boiler room at 95 I. Bohuna St. Over the past 4 years, significant wear and tear of the collectors, screen pipes, and convective part has been observed, which led to leaks and equipment shutdowns 4 times during the heating season and, accordingly, the cessation of coolant supply to consumers.

Socio-economic context

Indicator

Value

Number of people who will use the service

20139 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

District Heating

Stream

Modernization of the heating system (overhaul, reconstruction and arrangement of heating stations)

Strategic document

State Strategy for Regional Development for 2021–2027

Task

11 Modernization, adaptability and decarbonization of district heating systems

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Використано внутрішні звіти підприємства по підключеним абонентам та користувачам послуг.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
20139 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Expert report. Overhaul of the PTVM-50 boiler No. 2 (I. Bohuna boiler house, 95).pdf
03.03.2026
15:59:15 UTC

Alternative technical solutions

Technical Solution 1

Overhaul of water heating boiler No. 2 PTVM-50 of the boiler house at 95 I. Bohuna St. in the city of Kherson

Technical Solution 2

Installation of a cascade of modular gas boiler rooms

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)3'058'260 UAH142'200'000 UAH
For preparation0 UAH2'200'000 UAH
For implementation3'058'260 UAH140'000'000 UAH
Project operation and closure cost0 UAH10'000'000 UAH
For operation0 UAH2'000'000 UAH
For closing0 UAH8'000'000 UAH
Average annual costs1'500'000 UAH0 UAH
Project duration, incl.11 months15 months
Deadline for developing a FFS3 months5 months
Implementation period8 months10 months
Service life240 months300 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget3'058'260 UAH152'200'000 UAH
Project cost (preparation and implementation)3'058'260 UAH142'200'000 UAH
For preparation0 UAH2'200'000 UAH
For implementation3'058'260 UAH140'000'000 UAH
Project operation and closure cost0 UAH10'000'000 UAH
For operation0 UAH2'000'000 UAH
For closing0 UAH8'000'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitНа одного жителя, який користується послугами
Service Unit Cost152 UAH

Profitability of the project

Is the project expected to generate income?YesNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds3'058'260 UAH0 UAH
Expected Funds3'058'260 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
None of the options are applicable
Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Yes, negotiations are already underway.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Economic riskDefinedUndefined
Other riskDefinedUndefined

Team involvement

How exactly are/will stakeholders be involved?
Public hearings

[Response was provided in the Investment Feasibility Study]

When are/will engagement activities be taking place?
At the project implementation stage

[Response was provided in the Investment Feasibility Study]

How is/will the public be informed about the importance of participation and available channels for feedback?
Official websites

[Response was provided in the Investment Feasibility Study]

https://www.teploenergo.ks.ua/news
Are public hearings being held/will they be held (offline, online)?
Yes, online

[Response was provided in the Investment Feasibility Study]

Через безпекову ситуацію
Who will attend the public hearings?
Representatives of public organizations

[Response was provided in the Investment Feasibility Study]

Community representatives

[Response was provided in the Investment Feasibility Study]

Government officials

[Response was provided in the Investment Feasibility Study]

Public hearings have already been held
No

[Response was provided in the Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
07/03/2026SP-L-070326-ECB8CC0CCommunity SPInvestment Feasibility StudyInclude--
20/03/2026SPP-L-200326-053309D6Community SPPInvestment Feasibility StudyInclude-91